The final quantities of excavation were:
TRENCH: No. 1 11,115 cu. m.
No. 2 18,096 " "
No. 3 6,650 " "
--------------
Total 35,861 cu. m.
ROADWAYS: No. 1 4,165 cu. m.
No. 2 1,999 " "
No. 3 30 " "
-------------
Total 6,194 cu. m.
The route of the pipe line was laid out so as to obtain an average fill
of not more than 1 m. over the tops of the pipes, but in some cases the
cuts, for short lengths, were 3 m. deep. The excavation for this work
began in June, 1907.
_Hauling Pipes._--The pipes were hauled to the site of the work with
ox-carts and mule teams. The cost of hauling varied from 25 cents per
pipe at the lower end, to 1 peso per pipe at the upper and,
comparatively speaking, inaccessible portion of the line. The weight of
each 55.9-cm. pipe was about 182 kg.; that of each 63.5-cm. pipe was
about 216 kg.
The breakages in all the pipes cast at the pipe yard amounted to about
1%, due chiefly to unloading them carelessly near the pipe line.
_Pipe Laying._--The pipe-laying gang was composed of 7 Mexicans under
the direction of an American foreman, who was in charge of several
gangs. One gang could lay daily from 60 to 73 m. (from 100 to 120
pipes). The following was the ordinary pay-roll for one gang:
1 Foreman at 8 pesos (proportion). 2.00 pesos.
1 Pipe layer at 3 pesos. 3.00 "
1 Pipe layer's assistant at 2 pesos. 2.00 "
1 Cement mixer at 2 pesos. 2.00 "
2 Outside plasterers at 2.50 pesos. 5.00 "
2 Inside plasterers at 2.25 pesos. 4.50 "
1 Water boy at 0.50 peso. 0.50 "
-----------
Total. 20.00 pesos.
This brings the average cost of laying the pipes to 32.8 cents per lin.
m.
The pipes were jointed with 1:2 cement mortar, the outer joint being
rounded over both pipes for a width of 12-1/2 cm. (5 in.) and a height
of about 19 mm. (3/4 in.). In making these joints the pipe layers wore
rubber gloves. The joints were kept moist, and the trench was
back-filled with fine, screened material to a depth of 10 cm. above the
top of the pipe. Inside, the joints were carefully caulked with cement
and rendered smooth, the plasterers working continuously along with the
pipe layers, doing from 20 to 35 m. at a time. Water had to be conveyed
to the trenches by barrels on burros, and during the dry season it was
sometimes carried 5 or 6 km.
[Illustration: PLATE IV, FIG. 1.--TYPICAL REINFORCED CONCRETE GIRDER
BRIDGE, ESTANZUELA AQUEDUCT.]
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account