[Illustration: PLATE IV, FIG. 2.--ELLIPTICAL ARCH BRIDGE CARRYING
ESTANZUELA AQUEDUCT.]
_Bridges._--The line as laid out passed over many gulches and dry
arroyos, and these were crossed with reinforced concrete bridges of
varying spans and heights, two being shown on Plate IV.
These bridges were formed of continuous horizontal girders, 1.10 m. deep
and 1 m. wide, with a cantilever overhang at the abutments, varying in
length from 1 to 2 m., so as to avoid settlement between the pipes and
the bridges. The bottom reinforcement consisted of from 2 to 6 twisted
bars of mild steel, varying in different spans from 12.7 to 19 mm. (1/2
to 3/4 in.) in diameter. The turned up bars were 28-1/2 mm. (1-1/8 in.)
in diameter; they were placed on either side, carried over the upper
part of the beams, and continued along the end for the overhanging part
of the girder. These bars, when not obtainable of the full length, were
spliced with a lap of 1.2 m. with No. 6 galvanized-steel wire. The
vertical stirrups were 4.7 by 25.4 mm. (3/16 by 1 in.), of mild steel;
they were equally spaced 30.5 cm. (12 in.) apart, and carried all around
the girders, lapping at the center about 15 cm. (6 in.), all the steel
being carefully wired together before placing the concrete.
The general type of the piers and abutments is shown by Fig. 1, Plate
IV, and varies in height with practically every bridge, the foundations
in every case resting on hard rock. The concrete for the girders was a
1:2-1/2:3-1/2 mixture, the crushed stone used having all passed a mesh
of 19 mm. (3/4 in.). The piers were of 1:3-1/2:5-1/2 concrete, and heavy
"displacers" were embedded within them.
The concrete was placed after the pipes had been laid through the form
by the pipe contractor, the joints being kept clear of the bottom to the
required distance by small moulded concrete blocks. The tops of the
girders were moulded to a slightly segmental form. The bridges were all
kept watered for about 15 days, and the forms were not struck for 28
days after placing. At Station 13.4 the pipes were carried over a
picturesque arroyo on an elliptical arched bridge (Fig. 2, Plate IV) of
11 m. clear span.
The abutments of all bridges were protected by rubble walls in cement
mortar carried up 60 cm. above the tops of the girders.
The contract price for the concrete work of these bridges, the Company
furnishing the steel and cement, was 14 pesos per cu. m., and for
placing reinforcing steel 35 pesos per metric ton (2,204 lb.).
There are 49 single-span bridges, the larger spans being 9.10 m.; 8
two-span, and 11 three-span bridges, their total length, including the
overhang, amounting to 870.50 m., or 4-1/2% of the whole length of
aqueduct.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account