ASCE 1193: The Water-Works and Sewerage of Monterrey, N. L., Mexico: The 4th article from the June, 1911, Volume LXXII, Transactions of the American Society of Civil Engineers. Paper No. 1193, Feb. 1, 1911.Conway, G. R. G. (George Robert Graham)
Science
ASCE 1193: The Water-Works and Sewerage of Monterrey, N. L., Mexico: The 4th article from the June, 1911, Volume LXXII, Transactions of the American Society of Civil Engineers. Paper No. 1193, Feb. 1, 1911.
Fig. 10 is a plan of the reservoir, with a cross-section of the
excavation and embankment. On the lower side the original ground line
was cut down in steps, and all loose earth, roots, etc., were carefully
removed. The floor of the reservoir was chiefly sillar conglomerate, a
hard material that required a considerable amount of blasting for its
removal. The embankments were formed in 10-cm. layers of sillar and
conglomerate broken into small fragments and then rolled with 3-ton
sectional rollers drawn by teams of 4 and 6 mules, which assisted in
disintegrating the mass thoroughly, and produced by constant wetting a
homogeneous and compact clay. The excavation and embankment were left so
that 15 cm. of trimming could be done at a later date, immediately prior
to the lining of the reservoir. The excavated material amounted to about
34,000 cu. m., and, of this quantity, 31,500 cu. m. were used to form
the embankment; the remainder was taken to a spoil bank immediately
adjoining, the black earth stripping being separated and reserved for
covering the reservoir, etc. The contract prices for the excavated
material placed in the embankment were:
Pesos
per
cubic
meter
Class 1.--Material which could be removed by plows and scrapers 0.60
Class 2.--This consisted chiefly of "sillar" 1.09
Class 3.--Limestone conglomerate (requiring blasting) 1.65
The prices (for the same classification) for material taken to the spoil
bank, were 0.40, 0.80, and 1.40 pesos, respectively. Of the material
taken out, 15% came under No. 1 classification, 80% under No. 2, and 5%
under No. 3.
The excavation was begun at the end of May, 1907, and completed in
January, 1908, by Scott and Lee, the contractors. The embankments were
then allowed to stand until the beginning of July, 1908, to permit the
whole to become thoroughly settled and consolidated prior to beginning
the lining. In July the work of trimming the embankments and excavating
for the foundations of the reservoir columns was commenced, under the
Company's own administration, which completed the entire work.
[Illustration: PLATE VI.--DETAILS OF BEAMS AND COLUMNS FOR SOUTH
RESERVOIR.]
[Illustration: PLATE VIII, FIG. 1.--DETAILS OF FORMS FOR SOUTH
RESERVOIR.]
[Illustration: PLATE VIII, FIG. 2.--VIEW OF WESTERN HALF OF SOUTH
RESERVOIR, SHOWING FINAL SETTING UP OF DERRICK ON CENTRAL COLUMNS.]
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account