=26.= =Breaking Out a Sap from a Parallel.=--The head parapet
of a sap is about 2' 6" high. The parapet of a parallel is about 4' 6"
high. A sap of the usual form driven through the parapet of a parallel
will expose the latter to fire through the opening formed. To reduce
the danger from this exposure, the sap is broken out at night, and to
cover the opening in the shortest time two or three men may creep over
the parapet of the parallel and cover themselves by rapidly digging
a hole, from which they may work back and join the sappers, who are
working outward. The sap being driven obliquely to the front, the
trench widened, and the parapet made full size (Pl. II, Fig. 21), the
opening will be covered; or a few men may in some cases construct in
front of the parallel a short section of flying sap, under cover of
which the full sap may be broken out (Pl. III, Fig. 28).
Preliminary preparations for breaking out should be made during the
day, but should be so conducted as not to indicate the selected point
to the enemy.
=27.= =Circular places of arms= (Pl. IX, Fig. 83) may be
formed in front of a parallel by breaking out two single saps from
points 80 to 100 yards apart and so directing them as to meet at 25 or
30 yards in front of the parallel. They may be used by the guards of
the trenches or as depots for trench material, etc.
=28.= =Shallow Sap.=--When the presence of water in the
soil or of rock near the surface prevents driving the full sap 4' 6"
deep, a shallow or modified sap (Pl. II, Figs. 22 and 23) may be used,
provided a trench 3' deep can be driven forward. In this case Nos. 1
and 2 must both work kneeling, and Nos. 3 and 4 must throw the earth
well to the front and keep the parapet as high as possible, leaving
the construction of the berm to the widening party, who will give
to the trench the necessary width, and will then obtain earth for
strengthening the parapet by deepening the trench when practicable and
widening it when necessary, making, however, no irregularities which
will injure it as a communication and no depressions which will collect
water. This sap advances about as rapidly as the full sap.
=29.= =Overground Approaches.=--When the water or rock
comes to the surface of the ground, approaches can, under favorable
circumstances, be driven for short distances by carrying forward earth
in sand-bags, forming with them head and side parapets, and moving
forward by continually building up the latter and advancing the former
as before described.
The expenditure of time, labor, and sand-bags is so great in driving
approaches in this way that the minimum height of parapet (possibly 5')
should be made with sand-bags. This may be subsequently heightened and
strengthened with earth brought forward in barrows or hand-carts and
thrown upon the top and exterior slope.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account