(3) The continuity of surfaces should always be broken, at the same
time avoiding the formation of cavities and lines of cleavage. No
excavation to be refilled should have vertical sides, and long
continuous horizontal planes should be intercepted by wedge-shaped
offsets, enabling the dovetailing of materials together.
All loose and seamy rock or other porous material should be removed,
and where the refill is not the best for the purpose, mix the good and
bad ingredients thoroughly, after which deposit in very thin layers.
(4) Make the dimensions and profile of dam with a factor of safety
against sliding of not less than ten. The preliminary calculations for
designing such a profile have been given on p. 42.
(5) Aim at as nearly a homogeneous mass in the body of the embankment
as possible, thus avoiding unequal settlement and deformation. This
manner of manipulating materials will eliminate many uncertain or
unknown factors, but it means rigid inspection of the work and
intelligent segregation of materials, no matter what method of
transporting them may be adopted. The smaller the unit loads may
be, the more easily a homogeneous distribution of materials will be
obtained.
(6) Select earthy materials in preference to organic soils, with a
view of such combination or proportion of different materials as will
readily consolidate. _Consolidation is the most important process
connected with the building of an earth dam._ The judicious use of
soil containing a small percentage of organic matter may be permitted,
however, when there is a lack of clayey material for mixing with sandy
and porous earth materials. Such a mixture, properly distributed and
wetted, will consolidate well under heavy pressure and prove quite
satisfactory.
(7) Consolidation being the most important process and the only
safeguard against permeability and instability of form, use only the
amount of water necessary to attain this. Too much or too little are
equally bad and to be avoided. It is believed that only by experiment
and experience is it possible to determine just the proper quantity of
water to use with the different classes of materials and their varying
conditions. In rolling and consolidating the bank, all portions that
have a tendency to quake must be removed at once and replaced with
material that will consolidate; it _must not_ be covered up, no matter
how small the area.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account