Earthwork Slips and Subsidences upon Public Works: Their Causes, Prevention, and ReparationNewman, John
Science
Earthwork Slips and Subsidences upon Public Works: Their Causes, Prevention, and Reparation
Newman, John
Earthwork
39. Tipping an embankment in such a way as to promote consolidation.
In subsequent chapters many protective and remedial measures are
specifically named. Here reference is made to the more general
principles. The purpose for which a cutting has been excavated, or an
embankment deposited must be taken into consideration in providing
protective works, for the surfaces may only be temporarily bared, as in
trenchwork for walls, or be partly covered with water, as in canals, and
entirely unsubmerged upon one side as in canal, reservoir, and
reclamation embankments; or be fully exposed to meteorological
influences as in railway and road cuttings and embankments. There can be
no stereotyped system of operations for treating a slip, but experience
indicates that a frequently successful initiatory method is to divide
the earth into small portions, and to proceed to equally consolidate
them. However, in the case of deep cuttings, especially when excavated
in the side of a hill, it may be necessary to drive a heading beneath
the formation and to connect it with a shaft upon the higher side, so as
to tap the water-bearing soil, and to convey the water away to prevent
it reaching the slopes; this may be considered as a slip requiring an
exceptional remedy. Should a cutting be in moving ground or permeable
soil of doubtful stability, such a system of wells and covered
galleries, which are generally successful even in the worst soil, may be
required. The wells should, if possible, be sunk a few feet into an
impermeable stratum, their diameter being the least a man can excavate,
to any size required, and their distance apart, say, from 30 to 60 feet,
according to the quantity of water to be collected. They should be
connected by drifts. Smaller intermediate wells can be made between the
main wells. In order to be effectual such works must be carefully and
uniformly constructed, or an accumulation of water will arise. When a
slip is known to have occurred, simply from want of drainage, a
sufficient remedy may be the removal of the slipped earth and the
insertion of drains. An advantage of the loose counterfort system of
drainage as compared with rigid and fixed drains, is that open drains
will follow a slight subsidence of the earth, and yet maintain their
efficiency, but care must be taken that they do not become choked. In
shifting or doubtful soil all works should be quickly finished, and in
sidelong ground it is best to commence drainage operations on the valley
side so as to tap the water, as if they are begun on the hill-side they
may, until through drainage is effected, form channels for the
accumulation of water, and cause a slip. The repairs of a slip can be
commenced at several places simultaneously if at short distances apart,
such as 20 feet or so, and, as a rule, it is preferable in an embankment
that the work proceeds towards the centre, and not from the central
portion to the slopes. It is advisable to make ditches or galleries in
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account