(1) _Warehouses and shops._ All warehouses and shops were destroyed by
demolition and fire.
(2) _Utilities._ Electric, water, gas, and communications systems were
put out of commission by demolition and removal of parts.
(3) _Locked basins and docks._ All locked basins and closures were
destroyed; walls of basins were collapsed by explosives.
(4) _Wharves and quays._ Demolitions destroyed the inshore 100 feet of
quay full width to a depth of 30 feet. Mines destroyed all cranes and
blew out the face of the quay in sections about 40 feet long, 30 feet
back, and 20 feet deep. Cranes usually are spaced about 75 feet apart.
(5) _Miscellaneous._ Delayed-action mines and booby traps were placed
at strategic places, even in sunken boats and ships.
(6) _Channels and harbors._
(_a_) Ships were sunk to block entrances to harbors.
(_b_) All mooring buoys and channel markers were removed.
(_c_) All boats and lighters available to the enemy were sunk adjacent
to quays, wharves, and piers.
(_d_) Wharf cranes and debris were blown into channels alongside
wharves and quays. (See figs. 49 through 53.)
15. OPERATIONS OF PORT REPAIR SHIP IN A CAPTURED PORT.
=a. General.= The port commander is responsible for the restoration of
the port’s facilities. He orders surveys made of the extent and nature
of the damage and from them determines what work is to be done and who
is to do it, sets priorities, and estimates time, personnel, materials,
and equipment required. Before actual repairs can be started, the
following preparatory work usually has to be done by Army and Navy
units:
(1) Extinguish fires and demolish unsafe structures.
(2) Sweep mines.
(3) Remove blockships.
(4) Remove booms and torpedo nets.
(5) Neutralize land mines and booby traps.
(6) Install AA and other protective works.
(7) Remove debris in water and on quays.
(8) Remove obstructions from exits to wharf areas.
[Illustration: _Figure 50. Masts of sunken freighter in harbor. The
enemy did a systematic job of sinking ships to block the harbor as much
as possible._]
[Illustration: _Figure 51. Sunken ships and bomb-wrecked quays give
some idea of the huge task of repair and construction in restoring the
port to usefulness._]
[Illustration: _Figure 52. Temporary bridge built on a keeled-over
freighter. Trucks are using it to unload a Liberty ship._]
(9) Install navigation aids and moorings.
=b.= Following are some of the jobs the port repair ship might be
required to do:
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account