Building -- Estimates; Factories -- Design and construction; Hardware
In making calculations of the amount of material to be removed, care
should be taken to note the existing levels of the ground and those
required by the drawings. The excavation should be figured (and made)
at least 1 foot greater than the size of the foundation, so as to
provide room for setting the masonry, pointing, etc.
Excavation for pipes, drains, etc. should be at least 9 inches wider
than the diameter of the pipe to be laid therein. If the soil in which
the excavation is to be made is of a loose and sandy nature that is
liable to crumble and slide, a slope, say of 3 inches horizontal to 1
foot vertical, should be allowed on both sides of the trenches. If the
latter are of considerable depth, it is sometimes necessary to curb or
shore up the sides, in which case an allowance should be made in the
estimate for the lumber required. If piles are required, they should be
figured at so much per linear foot, driven.
ACTUAL COST OF EXCAVATION
=8.= In order that an idea may be formed of the actual cost of
excavating various kinds of soils, figures based on work actually
performed are here given. On this work, for a day of 8 hours, a laborer
was paid $2, and a driver with a two-horse team, $4.
As a rule, one laborer can excavate about 7 cubic yards of sandy
soil in 8 hours. Thus, at the rate of 25 cents per hour, the cost
of excavating this kind of soil is about 28½ cents per cubic yard,
provided the material is wasted around the building. To this figure,
however, must be added 4 or 5 cents to cover the foreman’s wages, the
exact amount depending on the number of men under the foreman. This
brings the total cost per cubic yard to about 33 cents.
When the material has to be carted away, the cost is further increased.
A team with a driver can haul away about 20 cubic yards of soil in a
day if the haul is only about ½ mile. In order to do this, however,
an extra wagon must be at hand so that the laborers can be loading
one wagon while the team is hauling away the other. Thus, the cost of
hauling 1 cubic yard of excavated material ½ mile is 20 cents. The
total cost, therefore, of excavating 1 cubic yard of sandy soil and
hauling it ½ mile is 33 + 20 = 53 cents.
=9.= If the soil is compact gravel, the cost of excavating, including
the foreman’s time, will be from 34 to 65 cents per cubic yard,
depending on its hardness. It costs about the same to haul compact
gravel as it does to haul sandy soil.
The exact cost of excavating wet soil cannot be given, as the
conditions encountered may vary in each case. In a stated time, a
laborer will excavate nearly as much wet material as dry material, but
the conditions of sheet piling and pumping out water makes the price
uncertain.
Such excavation is usually carried on at a cost of from 75 cents to
$1.25 per cubic yard.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account