Building -- Estimates; Factories -- Design and construction; Hardware
In excavating rock, three men—one rockman and two laborers—usually
work together. For a day of 8 hours, the rockman receives $3 and each
laborer gets $2. Together, therefore, the wages of the three amounts to
$7 a day. These men will excavate about 6 cubic yards of rock in 1 day,
making the rock excavation cost $1.17 per cubic yard. To this must be
added the cost of explosives, which is about 10 cents per cubic yard,
and the wear on tools. This latter expense can hardly be estimated,
but may also be considered as 10 cents per cubic yard, thus bringing
the total cost of rock excavation up to $1.37 per cubic yard for rock
wasted at the building.
=10.= To sum up, excavation in sandy soil wasted around the building
costs 33 cents per cubic yard; if hauled ½ mile, it costs 53 cents
per cubic yard. If the soil is compact gravel and is wasted around
the building, excavation costs from 34 to 65 cents per cubic yard;
if hauled ½ mile, from 54 to 85 cents per cubic yard. Wet excavation
with no piling or pumping costs about the same as dry; with piling and
pumping, it costs from 75 cents to $1.25 per cubic yard. Rock work
costs $1.37 per cubic yard if wasted around the building. These figures
do not include the contractor’s profit.
CONTRACTOR’S METHOD OF FIGURING EXCAVATION
=11.= Besides the actual cost of excavation, the contractor, in
estimating, must include such items as office expenses, builder’s
profits, etc. The following method of figuring, which is employed by
the estimator of a large contracting firm in the eastern part of the
United States, will therefore be found useful. As in the preceding
case, the prices will be found to vary in different localities;
therefore, the figures given should only be used as a guide in
estimating.
The prices are based on labor at $2 per day of 8 hours and a two-horse
team and driver at $5 per day of 8 hours. The excavation is assumed
to be made in ground varying from made ground to a moderately stiff
clay. The prices do not include the cost of shoring or pumping, and
are based on the assumption that there is no frost of any account
while operations are being carried out. Four classes of excavation are
recognized:
1. Excavation in trenches up to 5 feet deep, excavated material spread
on site about trenches, including back filling around walls, costs from
40 to 50 cents per cubic yard.
2. Trenches from 5 to 10 feet deep, excavated material spread on site
adjacent to trenches, including back filling around walls, costs from
65 to 75 cents per cubic yard.
3. For cellars, or similar digging, up to 6 feet deep and having an
area large enough to use a plow for loosening the earth (say areas
50 ft. × 20 ft. and over), excavated material being spread on site
adjacent to work, costs from 33 to 38 cents per cubic yard if a scoop
can be used, and from 40 to 45 cents per cubic yard if the material
must be loaded on a wagon to haul it out of the excavation.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account