No essential change occurs in the form of the channel-way from the
Fountain Reservoir on the Croton, to the Receiving Reservoir on the
island of New-York; a distance of thirty-eight miles, except in
crossing Harlem River to reach the island, and in passing a deep valley
on the island, where iron pipes are used instead of the channel-way of
masonry to provide for the pressure consequent upon a depression from
the regular plane.
At these points the iron pipes descend and rise again, so that when
the water is flowing in the channel-way they will be constantly full.
Thus it will be perceived that the channel-way of masonry will never
be filled entirely, so as to occasion a pressure on all its interior
surface.
The surface of the Fountain Reservoir is 166⅙ feet above the level
of mean tide at the city of New-York; and the difference of level
between that and the surface of the Receiving Reservoir on the island
of New-York, (a distance of thirty-eight miles) is 47⅙ feet, leaving
the surface of this reservoir 119 feet above the level of mean tide.
From the Receiving Reservoir the water is conducted (a distance of two
miles) in iron pipes to the Distributing Reservoir, where the surface
of the water is 115 feet above the level of mean tide. This last is the
height to which the water may generally be made available in the city.
GENERAL CONSTRUCTION OF THE AQUEDUCT.
Plate I. is a section of the Aqueduct showing the form of the masonry
used in earth excavations. The foundation is formed with concrete; the
side walls of stone; the bottom and sides of the interior being faced
with brick, and the top covered with an arch of brick.
In forming the concrete a mortar is made by mixing three parts of
sand with one of hydraulic lime, and then mixing about three parts of
stone, broken to a size allowing them to pass through a ring an inch
and a half in diameter. Having thoroughly mingled the broken stone
and mortar, the concrete is placed in its proper position and form,
and brought into a compact state by using a _pounder_; and is then
suffered to remain until it set, or become indurated, before any work
is commenced upon it. The object should be to mix as many stones or
pebbles as will thoroughly bed in the mortar, allowing none of them to
come in contact, but all to be enveloped in mortar. This forms a body
which becomes indurated and makes a foundation under the whole length
of the Aqueduct like one continuous stone. It attains a degree of
hardness which gives it the appearance of the conglomerate bearing the
name of _Pudding-stone_, and is an article of the greatest importance
in forming foundations for walls of great weight; superseding in many
instances, where the soil is soft, the use of piles or other timber
foundation.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account