Sewage and sewerage of farm homes [1928]Warren, George M. (George Milton)
Science
Sewage and sewerage of farm homes [1928]
Warren, George M. (George Milton)
Sewage disposal, Rural; Sewerage, Rural
The ground should next be excavated to the proper depth for placing the
floors in both chambers. The settling chamber floor, being the lower,
should be placed first. Effort should be made to secure water-tight
work, a feature of especial importance where leakage might endanger a
well or spring. A concrete mixture of 1:2:4 is generally preferred (1
volume cement, 2 volumes sand, 4 volumes stone). The ingredients should
be of best quality and thoroughly mixed. The concrete should be poured
promptly and worked with a spade or flat shovel to make the face smooth
and eliminate pockets or voids within the mass.[10] Before the settling
chamber floor has hardened the form should be set upon the floor and the
concrete work continued up the sides. The pipe form for the submerged
outlet should be set. When the side walls of the settling chamber have
reached the bottom of the excavation for the siphon chamber, the siphon
trap with its connecting branch and short piece of pipe should be set to
proper line and grade and blocked in position. The floor of the siphon
chamber should now be poured and the form for that chamber placed thereon,
leaving a 6-inch or 8-inch space (according to the thickness of the
division wall) between the ends of the two forms. Pouring of all side
walls and the top slab should continue without stop, making the entire
structure a monolith.
[10] See footnote, p. 12. For more detailed information on form and
concrete work the reader is referred to U. S. Department of Agriculture
Farmers' Bulletin 1480-F, "Small Concrete Construction on the Farm."
=Steel reinforcement.=--To stiffen the cover slab and guard against
cracking, a little steel should be embedded in the concrete about 1 inch
above the inside top. For this purpose a strip of heavy stock fencing is
convenient and inexpensive. The line wires should be not less than No.
10 gauge (about 1/8 inch) and the stay wires not less than No. 11 gauge.
The reinforcement should be cut at manholes and fastened around manhole
openings. If desired a standard wire-mesh reinforcement weighing about
one-third of a pound per square foot may be used. Another alternative is
to use 14-inch round rods, spacing the crosswise rods 6 inches apart and
the lengthwise rods 12 inches apart. Poultry netting should not be used,
because of its lightness.
=Sewer from tank to distribution field.=--The length of this sewer depends
on the situation of the field and the fall to it. The size of the sewer
depends on the fall that can be obtained and the size of siphon. The table
in Figure 24 shows the minimum fall at which 4-inch, 5-inch, and 6-inch
sewers should be laid to take the discharge of the 3-inch and 4-inch
siphons specified. The line and grade should be set in the same manner
as for the house sewer (see fig. 18) and the construction should be as
specified under that caption.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account