Shafts are also sunk in soft ground by constructing a concrete or metal
shell resting on a cutting shoe on the surface. The material inside is
dug out and the shell sinks of its own or added weight. The first
section of the shell may be from 5 to 10 feet long. As this section
sinks other sections are added. This is called the caisson method. It is
advantageous in wet ground and when the shafts are to be left as a
permanent manhole. If a permanent shaft is to be left in an excavation
being braced with wood, the permanent lining should follow within 20 to
30 feet of the shaft excavation. This is done to avoid the difficulty of
maintaining a great length of temporary wood shaft with the danger of
collapse, or of blocks or other objects falling on the workers below.
The distance between shafts is controlled by the depth and size of the
tunnel, surface conditions, and the character of the material being
tunneled. Except where surface conditions are crowded the shallower the
cover to the tunnel the more frequent the shafts. The advantage of
frequent shafts lies in the possibility of removing excavated material
from the tunnel promptly, and in making ventilation of the tunnel
easier. The saving made by the construction of numerous shafts must be
balanced against the extra cost of the shafts. For the shallowest
tunnels the shafts are seldom placed closer than every 500 feet.
=165. Timbering.=—After the shaft has been excavated to the proper grade
the tunnel is struck out either by cutting through the wooden sheeting
or by removing portions of the caisson lining. Practically all tunnels
except those in solid rock must be framed to some extent. Some of the
types of frames used in tunnel construction are shown in Fig. 116.
Different combinations of these may be used in different classes of
materials. In solid rock which remains firm on exposure no timbering is
necessary. Where the roof only need be supported and the sides are
strong enough to be used for support, a timber “hitch” or frame
supported on the sides of the tunnel may be used. This is suitable for
loose rock roofs with solid rock sides. Timbering such as is shown in
the lower left hand corner of Fig. 116 becomes necessary in extremely
soft, wet, or swelling material, where the bottom and sides as well as
the roof tend to push in. The remaining frame in Fig. 116 shows a form
frequently used and lying between the two extremes indicated. In wet
tunnels a channel may be cut in the bottom below the sill for drainage
purposes as shown in this form. The needle beam method of timbering is
also shown in Fig. 116. This method of timbering is used mainly near the
heading because of the speed and ease with which it can be installed,
but it is undesirable because of the space occupied.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account