Track-laying began April 2,1887, but was greatly retarded by snow and
ice in the completed cuts, and by the grading, which was heavy. The
cuts were frozen more or less up to May 15th. The forwarding of grading
forces to Minot began April 6th, but it was a labor of considerable
magnitude to outfit them at Minot and get them forward to the work;
so that it was as late as May 10th before the entire force was under
employment.
The average force on the grading was 3300 teams and about 8000 men.
Upon the track-laving, surfacing, piling, and timber-work there were
225 teams and about 650 men. The heaviest work was encountered on the
eastern end, so that the track was close upon the grading up to the 10th
of June. Some of the cuttings and embankments were heavy. After the 10th
of June progress upon the grading was very rapid. From the mouth of Milk
River to Great Falls (a distance of 200 miles) grading was done at an
average rate of seven miles a day. Those who saw this army of men
and teams stretching over the prairie and casting up this continental
highway think they beheld one of the most striking achievements of
civilization.
I may mention that the track is all cast up (even where the grading is
easy) to such a height as to relieve it of drifting snow; and to give
some idea of the character of the work, it is noted that in preparing it
there were moved 9,700,000 cubic yards of earth, 15,000 cubic yards of
loose rock, and 17,500 cubic yards of solid rock, and that there were
hauled ahead of the track and put in the work to such distance as would
not obstruct the track-laying (in some instances 30 miles), 9,000,000
feet (board measure) of timber and 390,000 lineal feet of piling.
On the 5th of August the grading of the entire line to Great Falls was
either finished or properly manned for its completion the first day
of September, and on the 10th of August it became necessary to remove
outfits to the east as they completed their work, and about 2500 teams
and their quota of men were withdrawn between the 10th and 20th of
August, and placed upon work elsewhere.
The record of track laid is as follows: April 2d to 30th, 30 miles;
May, 82 miles; June, 79.8 miles; July, 100.8 miles; August, 115.4 miles;
September, 102.4 miles; up to October 15th to Great Falls, 34.0 miles—a
total to Great Falls of 545 miles. October 10th being Sunday, no track
was laid. The track started from Great Falls Monday, October 17th, and
reached Helena on Friday, November 18th, a distance of 98 miles, making
a grand total of 043 miles, and an average rate for every working-day
of three and one-quarter miles. It will thus be seen that laying a good
road was a much more expeditious method of reaching the Great Falls of
the Missouri than that adopted by Lewis and Clarke.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account