When the shaft or tower of brickwork was completed up to the top, 42
feet in height, the next step was to remove the blockings on which it
rested, and this being done the gravel was excavated and hoisted up, and
the shaft descended by its own weight.
The Rotherhithe shaft was only sunk forty feet in this manner; the
remaining twenty feet, in order to leave the opening for the Tunnel, was
constructed by under-pinning, or underlaying, as it was then termed. The
underlaying was commenced in the beginning of June.[10]
By July 4 they had got down to the level of the intended foundation of
the shaft, having passed into a stratum of gravel, black pebbles
embedded in greenish sand, with little or no water; from which
circumstance Sir Isambard was of opinion that it was unconnected with
the stratum of gravel above.
_July 12._--Engaged on a general drawing for the great shield, and
in preparing some instructions for moving the same (a very
intricate operation!)
_July 22._--Underlaying is a very laborious mode of proceeding. The
sinking of a wall well bound as the first, would evidently be the
best and cheapest mode for making another tower of 50 feet
diameter.
On the 28th Sir Isambard enters in his journal the following additional
observations upon the success of his plans for sinking the shaft:--
Considering the great labour necessary for securing the ground for
the underlaying, the waste of planking, and of shores, and the time
necessarily taken up in moving about, in securing and in baling
out the water, and the many causes of interruption, and the
imperfect way that things are done in underlaying, it is quite
conclusive that the original plan of making a shaft, by sinking the
structure, is the safest and the most economical. What is done is
sound, and when once in place, may be secured with foundations in a
very easy manner. The brickwork of the shaft is remarkably hard.
Had it been made with brick facings and rubble stone, it would
certainly be water-tight, and almost impenetrable by ordinary ways.
The _vertical ties_ and the _circular wall bands_ are not to be
dispensed with in a structure destined to be moved as the present
has been.
On August 11 the underlaying was completed, and preparations were made
for constructing a reservoir in the bottom of the shaft for receiving
the permanent pumps. This was finished on October 11, with great
difficulty, owing to the nature of the ground, which consisted of loose
sand containing a large quantity of water.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account