The entire problem of bridges is so intricate a phase of American railroad
construction as to demand attention in a subsequent chapter. In actual
railroad practice it is apt to demand a separate branch of engineering
skill, both in construction and in maintenance. We turn our attention back
to the main problem of the building of our railroad.
When all plans are finished, contracts remain to be divided and
sub-divided; for it would be a brave contractor, indeed, who in these days
would consent to essay himself, any considerable length of railroad line.
In fact, in recent work of heavy nature, the price is almost invariably
placed at an indefinite figure, a certain definite percentage of profit
being allowed the contractor on each cubic yard of rock or soil. In such a
case the contractor's business becomes far less a game of chance; he is,
in effect, the railroad's agent supervising its construction at a certain
set stipend.
Let us say that the construction on our railroad begins in the early
spring. As a matter of real fact it would not be halted long because of
adverse weather conditions. Even up in the frozen and uninhabitable wilds
of the Canadian Northwest, work has been prosecuted on the new Grand Trunk
Pacific throughout the entire twelve months. But in summer the
construction gangs rejoice. The great proposition of bringing mile after
mile of future railroad to sub-grade--the level upon which the cross-ties
are to be set--fairly sweeps forward under the genial warmth of the sun.
The construction is under the supervision of competent engineers, who are,
of course, under the direct supervision of the railroad's own
organization. Every six to twelve or fifteen miles of new line is divided
into sections, better known as residencies, for each is under the eye of
its own resident engineer. He reports to the construction engineer, who in
turn reports to the chief engineer of the railroad, an officer who reports
to no less person than the president of the company.
This great force--for each engineer has gathered about him a competent
staff of young men as expert with compass, with level, and with transit as
were the men who first projected the line--is in the field as quickly as
the contractor. They are to see him bring the line to sub-grade; to see
him place bridges and culverts, bisect high hills with cuttings, bore
tunnels through even higher hills and mountains, span deep valleys with
great embankments. To facilitate quick construction the residencies are
made numerous; work begins at as many initial points as possible. These
points, of course, are situated, where possible, close to water
communication or existing railroad lines, in order that material may be
brought with the least possible delay and expense.
* * * * *
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account