On the intermediate course is to be laid the surface layer of broken
stone.[17] It must be 2¹⁄₂ inches in depth, and the stones must be
practically uniform in quality, and as near an approach to a cube in
form as possible. Each stone used in this layer must have passed through
a 2¹⁄₂-inch circular hole, and all stones that are wedge-shaped, and do
not approach uniformity of measurement on their sides, are to be taken
from the road with properly shaped rakes, and no stones allowed to
remain which are not sound, strong, and equable in size and quality of
material. The stones are to be raked into an even layer, and the steam
roller passed over them twice or thrice. After this a quantity of fine
screened gravel or sand is to be thrown on and sufficiently sprinkled to
moisten the mass without “licking up.” The rolling is then to be
continued (working the roller backwards and forwards, gradually from the
gutter to the crown), with an occasional light watering of the pavement,
until the cross-section be exact according to specification, the
interstices filled in, the roadway firmly compacted and solid, and all
excess of binding removed from the surface of the finished pavement.[18]
Telford’s object was the complete separation of the road metal from the
subsoil by a firm and regular foundation, and this system has ever since
held its ground. The advantages to be gained in constructing a roadway
in this manner may be summed up as follows:--
(1.) Economy of construction, as a considerable quantity of metalling is
saved; only 3 inches of properly broken stone and a little binding
material being necessary, the foundation of the roadway (which really
carries the traffic) may be made of a quality of stone unsuitable for
road metal, or even of bricks or stones from old buildings that are
being pulled down.
(2.) The prevention of the rising up or “spewing” of the clay or other
soft material on which the roadway rests.
(3.) A solid foundation is secured which will successfully resist the
weight and percussion of the traffic.
(4.) The increased facility for the drainage of the roadway water being
ruinous to it.[19]
Instead of forming a paved or “pinned” foundation for macadamised
roadways, sometimes what is called “hard core” is placed at the bottom
of the road upon the surface formation.
This “hard core” is made of very heterogenous materials, often the waste
products of the house refuse depôt, and consists of ashes, old pots and
pans, meat tins, old bottles, shells, and a variety of similar articles;
sometimes the core is made of burnt ballast, but in no case does it make
so good a foundation as stones set by hand.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account