The Municipal and Sanitary Engineer's HandbookBoulnois, H. Percy (Henry Percy)
Science
The Municipal and Sanitary Engineer's Handbook
Boulnois, H. Percy (Henry Percy)
Municipal engineering; Sanitary engineering
On the road-bed thus formed and compacted, a bottom layer of stone of a
depth of 8 inches at the centre of the road, and gradually diminishing
to 6 inches at the kerb, is to be set by hand, to form a close, firm
pavement. The stones are to be laid, with their largest side down, in
parallel lines across the street, breaking joint as much as
practicable.[16] The width of the upper part of the stone not to be more
than 8 inches, nor less than 6 inches. The stone not to exceed 15 inches
in length. After being set closely together, the stones are to be firmly
wedged by inserting a bar in all possible places, and placing between
them stones as nearly as possible of the depth of the pavement, until
the whole is bound in position. Projections of the upper part of this
course are to be broken off, care being taken not to loosen the
pavement; and no wedging is to be done within 20 feet of the face of the
work being laid. The small interstices are to be filled in with stone
chips firmly wedged with hammers. The whole is to be thoroughly rammed
and settled to place, and all undue irregularities of surface broken
off.
On the foundation course must be laid an intermediate layer of broken
stones, varying in size from 3 inches in their greatest diameters to 1
inch in their smallest diameters. These irregular-sized stones may be
either the “tailings” of the screened stones, or may be raked from the
quarry, and placed on the roadway without being machine-broken; but they
must nevertheless be so laid as to compact solidly, and must be clean
broken stone, free from dust and dirt, and within the dimensions given
above. This intermediate course must be 4 inches in depth at the centre
of the roadway, gradually decreasing to 3 inches in depth at the
gutters; it is to be thoroughly rolled with the steam roller until it be
firm, compact, and solid. On its upper surface it must be identical in
rise and form to the cross-section of the finished pavement, as
specified above. In the laying of this course of stone a small quantity
of binding material is to be used, sufficient only to fill up the
crevices, and render this portion of the pavement solid. Preferably the
binding is to be of fine screened gravel or sand, which is to be
sufficiently watered during the process of rolling, so that the “licking
up” of the road material, and its adherence to the rolling-wheels may be
prevented.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account