On Fourth Avenue, north of Union Square to 33d Street, there were two
electric conduit railway tracks in the center of the roadway and a
horse car track near each curb part of the distance. The two electric
car tracks were used for traffic which could not be interrupted,
although the horse car tracks could be removed without inconvenience.
These conditions rendered it impracticable to disturb the center of
the roadway, while permitting excavation near the curb. Well-timbered
shafts about 8 x 10 feet, in plan, were sunk along one curb line and
tunnels driven from them toward the other side of the street, stopping
about 3-1/2 feet beyond its center line. A bed of concrete was laid on
the bottom of each tunnel, and, when it had set, a heavy vertical
trestle was built on it. In this way trestles were built half across
the street, strong enough to carry all the street cars and traffic on
that half of the roadway. Cableways to handle the dirt were erected
near the curb line, spanning a number of these trestles, and then the
earth between them was excavated from the curb to within a few feet of
the nearest electric car track. The horse car tracks were removed.
Between the electric tracks a trench was dug until its bottom was
level with the tops of the trestles, about three feet below the
surface as a rule. A pair of heavy steel beams was then laid in this
trench on the trestles. Between these beams and the curb line a second
pair of beams were placed. In this way the equivalent of a bridge was
put up, the trestles acting as piers and the beams as girders. The
central portion of the roadway was then undermined and supported by
timbering suspended from the steel beams. The various gas and water
pipes were hung from timbers at the surface of the ground. About four
sections, or 150 feet, of the subway were built at a time in this
manner. When the work was completed along one side of the street it
was repeated in the same manner on the other side. This method of
construction was subsequently modified so as to permit work on both
sides of the street simultaneously. The manner in which the central
part of the roadway was supported remained the same and all of the
traffic was diverted to this strip.
[Illustration: SUPPORT OF ELEVATED RAILWAY STATION AT 42D STREET AND
SIXTH AVENUE]
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account