Between 14th and 17th Streets, because of the proximity of the rock to
the surface, it was necessary to move the tracks of the electric
surface railway from the center of the street some twenty feet to the
east curb, without interrupting traffic, which was very heavy at all
times, the line being one of the main arteries of the Metropolitan
system. Four 12 x 12-inch timbers were laid upon the surface. Standard
cast-iron yokes were placed upon the timbers at the usual distance
apart. Upon this structure the regular track and slot rails were
placed. The space between the rails was floored over. Wooden boxes
were temporarily laid for the electric cables. The usual hand holes
and other accessories were built and the road operated on this timber
roadbed. The removal of the tracks was made necessary because the rock
beneath them and the concrete around the yokes was so closely united
as to be practically monolithic, precluding the use of explosives.
Attempts to remove the rock from under the track demonstrated that it
could not be done without destroying the yokes of the surface railway.
[Illustration: SUPPORTING ELEVATED RAILROAD BY EXTENSION GIRDER--64TH
STREET AND BROADWAY]
The method of undermining the tracks on Broadway from 60th to 104th
Streets was entirely different, for the conditions were not the same.
The street is a wide one with a 22-foot parkway in the center, an
electric conduit railway on either side, and outside each track a wide
roadway. The subway excavation extended about 10 feet outside each
track, leaving between it and the curb ample room for vehicles. The
construction problem, therefore, was to care for the car tracks with a
minimum interference with the excavation. This was accomplished by
temporary bridges for each track, each bridge consisting of a pair of
timber trusses about 55 feet long, braced together overhead high
enough to let a car pass below the bracing. These trusses were set up
on crib-work supports at each end, and the track hung from the lower
chords. (See photograph on page 42.) The excavation then proceeded
until the trench was finished and posts could be put into place
between its bottom and the track. When the track was securely
supported in this way, the trusses were lifted on flat cars and moved
ahead 50 feet.
At 66th Street station the subway roof was about 2 feet from the
electric railway yokes and structures of the street surface line. In
order to build at this point it was necessary to remove two large gas
mains, one 30 inches and the other 36 inches in diameter, and
substitute for them, in troughs built between the roof beams of the
subway, five smaller gas mains, each 24 inches in diameter. This was
done without interrupting the use of the mains.
[Illustration: MOVING BRICK AND CONCRETE RETAINING WALL TO MAKE ROOM
FOR THIRD TRACK--BROADWAY AND 134TH STREET]
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account