Several old French ladder dredges were rescued from the jungle and put
into commission at the beginning of the work, and they held out
faithfully to the end, dividing honors with the newer equipment in
hastening the day when the oceans might go inland to Gatun and
Miraflores. While they looked like toys beside such giant excavators
as the Corozal, they probably showed more efficiency than any other
class of excavators of their period of construction. They were
attended by large self-propelling scows built by the French. When
these were filled they steamed out to sea and dumped their burden and
then steamed back again for another load. Some of the dredges were
attended by ordinary barges which were towed out to sea by tugs and
dumped.
Another interesting machine used on the Pacific end of the canal was
the Lobnitz rock breaker. This consists of a sort of pile driver
mounted on a large barge. Instead of a pile driving weight there is a
big battering ram made of round steel, pointed at one end. It is
lifted up perhaps 10 feet and allowed to drop suddenly. As some of
these rams weigh as much as 25 tons their striking force may be
imagined. When the ram struck the rock the top would shake back and
forth like a bamboo pole, in spite of the fact that it was made of the
best steel and more than 15 inches in diameter. Sooner or later the
rams would break off at the water line, this being due to the fact
that the constant flexion at that point set the molecules in the steel
and took away all its elasticity.
It was found desirable to excavate a part of the sea-level channel
before the water was let into it. To accomplish this a big dam, or
dike, was built across the channel several miles inland, and steam
shovels were used behind this dike. As the work neared completion,
however, it was found advisable to let the water come further inland,
so that the dredges could extend the field of their activities. To do
this another dike was thrown across the channel about a mile north of
the first one, and water was admitted to the section of the big ditch
between these two dikes. The engineers were afraid to cut a small
ditch in the top of the first dike, and allow the water to eat the dam
away as it flowed in, for fear that it would rush in so rapidly it
would destroy the second dike. Therefore they filled the basin between
the two dikes by siphon and by pumping, a process which required the
drawing in of billions of gallons of water. This was accomplished in
due time, however, and then 16 tons of dynamite was placed in the no
longer useful dike. An electric spark did the rest.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account