Upon the Atlantic Division, during the fiscal year 1908–’09, a dredging
fleet consisting of one sea-going suction dredge, two 5-yard dipper
dredges and three French ladder dredges worked on the section between
Mindi and deep water, removing 6,039,934 cubic yards, of which 427,005
cubic yards were rock. The rock is removed by blasting. Holes averaging
15 feet apart are drilled to a depth of 50 feet below sea level, loaded
with dynamite and fired. At the close of the year nearly 3 miles of the
channel from deep water were completed.
The plans for breakwaters in Limon Bay were recently changed.
Originally breakwaters were planned to extend nearly parallel to the
axis of the channel to protect against filling by wave action. However,
it was found that the northers entering between these breakwaters would
lack room to dissipate and so vessels would be unprotected for a great
portion of the distance to the locks. Accordingly two breakwaters have
been planned which are to be so placed as not only to prevent filling
but also to give shelter to shipping.
On the Culebra section of the Central Division considerable trouble
has been caused by the great rainfall. To carry the rain off quickly
diversion channels have been constructed at a large expense of money
and labor.
Water falling in the prism is cared for by the cut itself. In the
process of deepening pilot cuts are started from either end towards
the summit which is now between Empire and Culebra. Drainage in either
direction is by gravity through these cuts.
The total amount excavated from the canal prism in this division during
the past year was 18,442,624 cubic yards, 12,291,472 cubic yards being
rock. At the close of the year 43,574,954 cubic yards remained to
be removed. The material is loaded on the cars by steam shovels, is
hauled to the various dumps, and unloaded by a huge plow-like apparatus
which is drawn from end to end of the train. Part of the spoil aided
in the rebuilding of the Panama Railroad; the rock from Empire and
Bas Obispo went to Gatun for the dam, and some material was hauled to
Balboa on the Pacific and was there used in reclaiming ground and in
building a breakwater in Panama Bay to cut off silt-bearing currents
which were filling up the excavated channel. It has been built out
about 2 miles by dumping from a trestle built for the purpose. One mile
more remains to be built.
The slides in Culebra Cut have continued. The largest, called the
Cucaracho slide, measures 2,700 feet along the cut, involving an area
of 27 acres. During the year 1908–’09, 670,017 cubic yards were removed
from this slide but it is estimated that 700,000 more are still in
motion. Drainage seems to be ineffectual in these cases.
The original summit at Culebra Cut was 333 feet above the sea; it was
lowered by the French to 157 feet and the lowest point at the summit is
now 143 feet above sea level.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account