The lake section of the Central Division extends from Gamboa to Gatun.
The Chagres River here crosses the line of the canal 23 times, forming
a series of peninsulas. A portion of the channel 2,700 feet long, 500
feet wide at the bottom and 50 feet deep, was completed May 25, 1909
and the waters of the Chagres turned in. A total of 1,784,459 cubic
yards were taken out, of which 1,350,308 were removed in 1908–’09. From
the remainder of this division 2,625,283 cubic yards were excavated in
1908–’09.
To secure the necessary width and depth between Pedro Miguel and
Miraflores on the Pacific Division 1,279,600 cubic yards of material,
of which 63,600 are rock, must be excavated. The material still to be
taken out between Miraflores and deep water is 13,000,900 cubic yards
of loam and 1,725,000 cubic yards of rock. It has been decided to
remove all rock between the locks and for 2 miles below the Miraflores
locks, in the dry. This will leave 3,600,000 cubic yards of loam and
123,000 of rock to be removed by dredging and blasting.
The dredging fleet in Panama Bay for 1908–’09 consisted of one
sea-going suction dredge, one 20 inch suction and pipe-line dredge,
one 5 yard dipper dredge, and four French ladder dredges. They removed
8,475,931 cubic yards of material during the year. The channel is
completed for about 5 miles from deep water in the Pacific.
The entire present steam-shovel equipment on the Isthmus consists
of forty-eight 95-ton, forty-two 70-ton, ten 45-ton, and one 38-ton
steam-shovels, or a total of one hundred and one steam-shovels.
Dry excavation for the first quarter of the fiscal year 1908–’09, (July
1 to October 1), cost 63 cents per cubic yard for direct charges and 12
cents per cubic yard for general administration, making a total of 75
cents. Dredging cost 9 cents per cubic yard for direct charges and 2
cents per cubic yard for general administration. The average cost per
cubic yard for excavation was 40 cents for direct charges and 8 cents
for general administration, making a total of 48 cents.
VIII. CONSTRUCTION OF THE LOCKS
_Locks_
As before stated there are to be 6 locks on the Panama Canal, 3 at
Gatun, 1 at Pedro Miguel and 2 at Miraflores. All of these locks are
arranged in duplicate, i.e., at any group of locks a vessel may ascend
at one side of the middle wall, while another is descending at the
other side. It is the intention that Pacific bound vessels use one side
and Atlantic bound the other.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account