Stephenson was called upon to cope with another critical situation
upon the same railway. The great tunnel at Kilsby was in course of
construction, but work had not proceeded very far when the contractors
struck a large pocket of water and quicksand. They combated this
adversary for several months, and then, unable to make any appreciable
headway, threw up the contract. Efforts were made to induce other
firms to accept the task, but in vain. At last Stephenson was called
upon to rescue the undertaking from failure. The outlook was far from
promising, for the shaft was being sunk through material which the
engineer always regards askance--a shale--while the fault in which
reposed a large volume of water and sand was of large proportions.
Stephenson concluded that the best way to cope with the problem was to
pump out the water first, and accordingly he rigged up an elaborate
plant capable of handling 1,800 gallons per minute, and this was kept
going day and night. Even then, however, it was only by superhuman
effort that the water was kept down. One day after Stephenson had been
on the scene about six months, the water got the upper hand and flooded
the tunnel to such a depth that the men and materials had to be floated
in on rafts.
This undertaking, however, served to demonstrate to those anxious to
participate in railway-building speculations how estimated expenses
for definite work might be sent astray seriously, and how formidable
and ubiquitous was the unexpected factor in such work. The original
contractor offered to complete the burrow, 7,169 feet in length, under
the Kilsby Ridge for some £90,000. By the time the last brick of the
lining had been laid and the tunnel was ready for use over £300,000 had
been expended.
The attempt to pierce this tunnel at that time, however, was a far more
difficult enterprise than it would be to-day. The engineers had not the
powerful marvellous appliances such as serve the contractor’s purposes
now. Electric energy was unknown, the hydraulic shield for driving
tunnels had yet to be invented, the steam shovel had not been thought
of--in short, the contractor was handicapped on every side by the crude
character of his tools. Some of these appliances which the modern
railway-builder uses are little short of wonderful, both in time- and
labour-saving qualities, and the majority have been born of necessity.
For instance, in the early railway days on the American continent
too much time would have been occupied in building lofty earthen
embankments among the mountains. Accordingly the rifts and gullies were
spanned by timber trestles. But the woodwork was perishable, and there
was always the risk of fire demolishing the structure and precipitating
disaster to a passing train. The obvious remedy was to replace the wood
by metal, but the expense was a deterrent factor.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account