Monday, May 31st, 10 A.M., hove to, lat. 47° 11´, long. 9° 37´. Up
to midday engaged in making splice between experimental cable in
fore coil and that in main hold, besides other minor operations. In
afternoon getting hawser from Niagara and her portion of cable to
make joint and splice. 4 P.M., commenced splice; 5.15 splice
completed; 5.25, let go splice-frame (weight 3 cwt.) over gangway,
amidships, starboard side.[27] 5.30, after getting splice-frame
(containing the splice) clear of the ship and lowering it to the
bottom, each vessel (then about a quarter of a mile apart)
commenced paying out in opposite directions.
9 P.M., got on board Niagara's warp and her end of cable to make
another splice for second experiment.
June 1st.--1 A.M. (night), electrical continuity gone, the cable
having parted after two miles in all had been paid out.[28]
Since 1 A.M., engaged in hauling in our cable. Recovered all our
portion, and even managed to heave up the splice-frame (in perfect
condition), besides 100 fathoms of Niagara's cable, which she had
parted. Fastened splice to stern of vessel and ceased operations.
9.23 A.M., second experiment. Started paying-out again. Weather
very misty.
9.40, one mile paid out at strain 16 cwt.; angle of cable 16° with
the horizon: running out straight; rate of ship 2, cable 3.
9.45, changed to lower hold. 9.56, two miles out; last mile in
16-1/2 minutes; strain 17 to 20 cwt.; angle of cable 20°. 10.10,
last of the three miles out in 14 minutes.
10.32 A. M., four and a half miles out. Third experiment--stopped
ship, lowered guard, stoppered cable.
10.50, buoy let go, strain 16 cwt. when let go, the cable being
nearly up and down.
11.6, running at rate of 5-1/2 knots paying out, strain 21 to 23
cwt., varying. Cable shortly afterward parted through getting
jammed in the machinery.
The subsequent experiments were mainly in the direction of buoying,
picking up, and passing the cable from the stern to the bow sheave for
picking up. All of these operations were in turn successfully performed;
and finally, in paying out a speed of seven knots was attained without
difficulty. During all this time electrical communication had been
maintained between the ships; and it is somewhat remarkable that,
through this more or less damaged cable, the electricians were able to
work a needle-instrument and obtain a deflection on it of 70 degrees.
[Illustration: FIG. 25.--Experimental Maneuvers in the Bay of Biscay.]
And now, the program being exhausted, the ships returned to Plymouth. On
the whole, the trip had proved eminently satisfactory. The paying-out
machinery had worked well, the various engineering operations had been
successfully performed, and the electrical working through the whole
cable was perfect.
CHAPTER VI
THE STORM
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account