Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910: The New York Tunnel Extension of the Pennsylvania Railroad,; The North River Division. Paper No. 1151 — John Shaqi
Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910: The New York Tunnel Extension of the Pennsylvania Railroad,; The North River Division. Paper No. 1151Jacobs, Charles M. (Charles Mattathias)
History
Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910: The New York Tunnel Extension of the Pennsylvania Railroad,; The North River Division. Paper No. 1151
Jacobs, Charles M. (Charles Mattathias)
Civil engineering -- Periodicals; Railroad tunnels -- Design and construction
Compressed air, at an average gauge pressure of about 25 lb. and a
maximum of 40 lb. per sq. in., was used in the tunnels from the time the
shields emerged from full rock face until the tunnel lining had been
joined up and all caulking and grummeting had been done.
[Illustration: FIG. 5.--(Full page image)
ARRANGEMENT OF STRUCTURES SUPPORTING NINTH AVE. DURING PROGRESS OF
EXCAVATION]
Contractor's plants were established at the Weehawken Shaft and at the
Manhattan Shaft, including at each, low-pressure air compressors of a
capacity of 13,000 cu. ft. of free air per minute and also high-pressure
air compressors for drills, hydraulic pumps, electric generators, etc.
The river tunnels passed under Pier 72, North River (old No. 62), which
was occupied by the New York Central and Hudson River Railroad Company.
The Tunnel Company leased this pier and withdrew all the piles on the
lines of the tunnels prior to the commencement of construction, and on
the remaining piles constructed a trestle for the disposal of the
excavation from the tunnels and the terminal. At the completion of the
work this pier had to be restored, and Fig. 10 shows the general
arrangements of the location of the piles and the pier structure with
reference to the tunnels.
In the tunnels which were constructed in silt farther down the river, by
the writer as Chief Engineer for the Hudson Companies, it had been
possible to shove the shield through the silt with all the doors closed,
displacing the ground and making great speed in construction owing to
the absence of all mucking. It was thought that this procedure might be
pursued in the larger tunnels of the Pennsylvania Railroad, and it was
tried, but it was almost immediately found to be impossible to maintain
the required grade without taking a certain quantity of muck into the
tunnels through the lower doors, the tendency of the shield being to
rise. By taking in about 33% of the excavation displaced by the tunnel,
the grade could be maintained. It was considered desirable, owing to
this rising of the shields, to increase the weight of the cast-iron
lining, and this was done, making the weight of the completed tunnel
more nearly equal to the weight of the displaced material. The weight of
the cast-iron lining (with bolts) was increased from 9,609 to 12,127 lb.
per lin. ft. of tunnel. The weight of the finished tunnel with this
heavier iron is 31,469 lb. per lin. ft. The weight of the silt displaced
per linear foot of tunnel, at 100 lb. per cu. ft., is 41,548 lb. The
weight of the completed tunnel with the maximum train load is 42,869 lb.
per lin. ft.
The maximum progress at one face in any one month was 545 ft., working
three 8-hour shifts, and the average progress in each heading while
working three shifts was 18 ft. per 24 hours; while working one shift
with the heavier lining referred to above, the delivery of which was
slow, the average progress was 11 ft. per 24 hours.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account