The tunnel engines left the cars on a track just outside the portal,
from which they were made up into trains of from 6 to 8 cars and taken
to the dump or crusher by the large “dinky.”
The muck from the Central Shaft headings was loaded by hand into cars
similar to that shown by Fig. 5, but smaller and having no door at the
forward end. A double elevator took the cars to a platform about 20 ft.
above the surface, where they were dumped by revolving platforms,
similar to those at Weehawken, into storage bins or directly into
wagons. The muck was all hauled away in wagons; part of it was used to
fill some vacant lots, and part was hauled to the crusher at the Western
Portal.
The method under which the best results were obtained was that in which
a full round was blasted every 36 hours, securing an advance of
practically 9 ft. of full section. During the first shift of the three,
as soon as the blasting had been completed and lights strung, the shovel
was moved forward, and cleaned up the floor to the main pile of muck,
the material from the blast being scattered from 150 to 300 ft. back
from the face; during this shift, also, the drillers mucked the heading
and set up their drills, the muckers helping to carry in the columns and
drills. During the second shift the main pile of muck was disposed of,
leaving not more than 2 or 3 hours’ work for the shovel on the third
shift. This left nearly the whole of the third shift for drilling the
lift holes.
_Ventilation._--At Weehawken considerable difficulty was caused by fog
and smoke accumulating in the tunnels after blasting. This was generally
worse on days when the barometric pressure was low outside, and worse in
the North than in the South Tunnel. A 6-ft. fan, driven by an electric
motor, was installed in the cross-passage at Station 274, 900 ft. from
the shaft, the headings at that time being about 300 ft. in advance of
this point, to force the air from the South into the North Tunnel,
drawing it in at the mouth of the South Tunnel and discharging it at the
mouth of the North Tunnel, thus insuring a circulation in both tunnels,
as shown in plan by Fig. 8.
[Illustration: Fig. 8.]
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account