This necessitated, of course, that the cross-passages between that in
which the fan was placed and the mouths of the tunnels should be blocked
tight. There was some difficulty in keeping this blocking tight, owing
to the force of the blasting blowing out the bulkheads. The fan,
however, did good service when it and the bulkheads were in good order.
The compressed air discharged from the drills kept the headings fairly
clear, as well as that part of the tunnel between the headings and the
fan. The fan was moved ahead to the next cross-passage at Station 277
when the work had progressed far enough, and was used there for some
time; it was found, however, that by the time the excavation had reached
Station 280, about 1,500 ft. from the shaft, there was practically no
further difficulty from fog and smoke. No satisfactory explanation was
found for this, as it would rather be expected that the ventilation and
trouble with smoke and fumes from blasting would be worse as the
distance increased between the mouth of the tunnel and the working face.
One explanation was offered: That the blasting of the softer sandstone
tended to create more and lighter dust than the heavier trap rock;
whether or not this was so, it is a fact that there was far less trouble
with fog and smoke after the sandstone was passed.
At Hackensack, the principal cause of trouble was the smoke from the
“dinky” locomotives. As the tunnels progressed, this gradually became
worse, until a connection was made with the Central Shaft headings.
A fan was installed in the cross-passage at Station 316 (700 ft. in from
the portal), but was never worked properly. Apparently, the men, at
least the walking bosses and foremen, had little faith in the fan as a
means of ventilation; no real attempt was made to keep it in order or
operate it properly, and a great deal of time and money was lost groping
around in the smoke and fog, the density of which increased, not only
with the state of the atmosphere, but also with the direction of the
wind. On some days the tunnels easily cleared themselves, and on others
the smoke was so thick that a candle held at arm’s length could not be
seen. At this end, the South Tunnel was generally worse than the North.
After the headings were holed through between the portal and the Central
Shaft there was very little trouble, there being usually a strong
up-draft through the shaft. This was so pronounced when the wind was
blowing toward the portal, that the moisture-laden air, as it ascended
from the mouth of the shaft, presented the appearance of a heavy
rainstorm with the rain ascending instead of descending. When the wind
was blowing away from the portal, that is, from the southeast, the
effect of the shaft as a chimney was neutralized, and, consequently, the
smoke accumulated in the tunnels. To overcome this, a large blower, with
a fan 9 ft. in diameter, and with blades 4 ft. wide and 2 ft. 3 in.
long, operated by a vertical 12-h.p.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account