Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910: The Bergen Hill Tunnels. Paper No. 1154Lavis, F.
History
Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910: The Bergen Hill Tunnels. Paper No. 1154
Lavis, F.
Civil engineering -- Periodicals; Railroad tunnels -- Design and construction
[Footnote 2: Plate VIII of the paper by Mr. Jacobs.]
The quantities of the various materials in the lining, per linear foot
of tunnel, were as follows:
Concrete 7.64 cu. yd.
Rock packing: Paid for 1.48 cu. yd.
Outside standard section line 1.74 ” ”
------------ 3.22 ” ”
Iron and steel 44.2 lb.
Vitrified conduits 84.0 duct ft.
Water-proofing 13.0 sq. ft.
Flags 3.3 ” ”
_General Methods._--The lining was started at both ends of the tunnels
before the headings were finally holed through, so that there was
practically a separate organization at each end, each in charge of one
of the members of the firm. The work at the Weehawken end was started
first, and the plant and scheme of working adopted there was thoroughly
tried out before the plant for the western end was built, consequently,
the latter was somewhat more efficient, being designed in the light of
the experience gained at the Weehawken end.
The general sequence of the plan first adopted in placing the concrete
is shown by Fig. 10. The concrete was first placed in the foundations up
to the elevation of the bottom of the conduit bines, this work, of
course, being kept well in advance; next followed, in the order named,
the sand-walls, water-proofing, conduits, bench-walls, and finally the
arch. The foundation was built in any convenient lengths, multiples of
16 ft., the length of one section of form, the sand-walls in lengths of
from 25 to 35 ft., the bench-walls in 25-ft. lengths, and the arch in
10-ft. lengths. Concrete was placed during the day shift only, the forms
being moved partly at night, and partly on the alternate days when
concrete was not being placed in them.
Five gangs were organized at each end, the first placed concrete in the
foundations in both tunnels, as the excavation was ready. In each tunnel
there was a gang which built sand-wall one day and bench-wall the next,
the two tunnels alternating so that only one bench-wall was built each
day, and finally a gang in each tunnel building arches, a 10-ft. section
being completed each day. During the night shift, the arch forms and
travelers were moved, and all other forms, etc., were made ready for the
concrete to be placed the following day. Some of the conduit laying was
done by the night shift, but part of it was necessarily done during the
day, as the concrete was built up. A small gang was kept busy in both
tunnels, during the day shift, laying conduits and water-proofing. The
latter two operations were generally performed by the same gang.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account