In November, 1867, 33 feet, 1272 feet.
December, 1867, 22 feet, 1294 feet.
January, 1868, 33 feet, 1327 feet.
February, 1868, 35 feet, 1362 feet.
March, 1868, 34 feet, 1396 feet.
April, 1868, 24 feet, 1420 feet.
May, 1868, 26 feet, 1446 feet.
June, 1868, [3] 21 feet, 1467 feet.
July, 1868, (Nitro-Glycerin used) 47 feet, 1514 feet.
August, 1868, “ 44 feet, 1558 feet.
September, 1868, “ [4] 51 feet, 1609 feet.
[3] Preparing for machine drilling.
[4] September 1, to 24, 5-6 month. Rate 61 feet per month.
“But for the improved methods of working introduced, the advance would
have been much less satisfactory than that we are enabled to exhibit
above.
“Concerning the employment of Nitro-Glycerin and machine drilling at
West Shaft, it is hardly necessary to remark that many difficulties
are to be encountered in the training of men to a new service and in
successfully employing a new description of fuse and explosive. Some
remarks upon our experience in blasting with this compound, will be
found in a subsequent portion of this report. Continuous use of machine
drills was commenced at the West Shaft in the latter part of June, and
of Nitro-Glycerin as an explosive in the month of August. Some delays
were necessarily experienced at first, but greatly improved progress
was shortly attained. Some previous trials of machine drilling had been
made earlier in the present year, but without continuous progress,
upon which satisfactory estimates of success might be based. The last
workings made, including the month of September, up to the time of
suspension, about five-sixths of a working month, attained a linear
progress of 51 feet, with six drills only. The machinery provided at
West Shaft is only sufficient to supply the pneumatic power for the
ordinary working of the above number, to which accordingly we have been
necessarily confined.
The two drill carriages employed are larger than those at East End, and
are intended to carry five drills each—in all, ten drills working at
the breast of the heading. Assuming, as we may safely, that the rate of
progress is proportional to the number of drills employed, ten drills
would advance 100 feet per month; and with full power provided and
further experience to be acquired by the workmen, this and even greater
average rates of monthly progress can be made and maintained.
These headings are run at top, i.e., above the excavations hereafter to
be made, and of such height, and top outline as to correspond with the
roof of the completed tunnel.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account