When the face of the bench had been brought to within 3 or 4 ft. of the
forward end of the wall plate, the process of widening out and timbering
another 20 ft. length of heading was begun. In some places the rock,
though needing permanent support, was such that the work of taking out
the bench and widening the heading was carried on simultaneously without
increasing the danger; but the greater portion of the work, when
strutting was required, was done as has been described.
[Illustration: FIG. 66.--Diagram Showing the Arrangement of Drill Holes
in the Heading and Bench of the Gallitsin Tunnel.]
=Hauling.=--The excavated material was loaded at the foot of the bench
in dump cars which were run by mule power to the portal or the shaft
according to location, on 36 in. gauge-service tracks. Inclines at 159th
Street were graded from the portal at 158th Street to the street
surface. The cars were formed at this portal into a train and were taken
up the incline to the dump at 162nd Street and the North River by
construction locomotives. At the 168th Street and 181st Street shafts,
the cars were hoisted to the surface in cages (elevators). In the former
case, they were taken to the dump at 165th Street and the North River by
mules and gravity; in the latter case, to various dumps by teams. At
both shafts, stone crushers were located, therefore a great part of the
material did not have to be hauled to the dumps or even taken to the
surface as a great deal of stone was used in dry packing over the
concrete arch. The material from the portal at Fort George was hauled by
mules directly to the dump near by.
=Lining.=--The entire tunnel was lined with concrete, consisting of a
floor 4 ins. thick and vertical side walls 18 ins. thick and 25 ft.
apart, which carried a semicircular arch 18 ins. thick except in the
timbered portions where the thickness was increased to 21 ins. and to 24
and 27 ins. in some places. The springing line of the arch is 6 ft. 2
ins. above the concrete floor (5 ft. 6 ins. above the base of rail),
hence the maximum clearance above the base of rail is 18 ft. The side
walls and arch were built solid of rock to a height of 8 ft. above
springing line and the space above that point between the concrete and
the rock was packed by hand with small stones. The concrete of the arch
was laid on timber centers erected for that purpose.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account