=Strutting.=--The longitudinal method of strutting, with the
poling-boards running transversely of the tunnel, is always employed in
the Belgian method of tunneling. In driving the first center top
heading, pairs of vertical posts carrying a transverse cap-piece are
erected at intervals. On these cap-pieces are carried two longitudinal
bars, which in turn support the saddle planks. As fast as part No. 2,
Fig. 68, is excavated, the vertical posts are replaced by the batter
posts _A_ and _B_, Fig. 69. The excavation of parts No. 3 is begun at
the top, the poling-boards _a_ and _b_ being inserted as the work
progresses. To support the outer ends of these poling-boards, the
longitudinals _X_ and _Y_ are inserted and supported by the batter posts
_C_ and _D_. In exactly the same way the poling-boards _c_ and _d_, the
longitudinals _V_ and _W_, and the struts _E_ and _F_, are placed in
position; and this procedure is repeated until the whole top part of the
section is strutted, as shown by Fig. 69, the cross struts _x_, _y_,
_z_, etc., being inserted to hold the radial struts firmly in position.
The feet of the various radial props rest on the sill _M N_. These
fan-like timber structures are set up at intervals of from 3 ft. to 6
ft., depending upon the quality of the soil penetrated.
[Illustration: FIG. 69.--Sketch Showing Radial Roof Strutting, Belgian
Method.]
[Illustration: FIG. 70.--Sketch Showing Roof Arch Center, Belgian
Method.]
=Centers.=--Either plank or trussed centers may be employed in laying
the roof arch in the Belgian method, but the form of center commonly
employed is a trussed center constructed as shown by Fig. 70. It may be
said to consist of a king-post truss carried on top of a modified form
of queen-post truss. The collar-beam and the tie-beam of the queen-post
truss are spaced about 7 ft. apart, and the posts themselves are left
far enough apart to allow the passage of workmen and cars between them.
The tie beam of the king-post truss is clamped to the collar-beam of the
queen-post truss by iron bands. On the rafters of the two trusses are
fastened timbers, with their outer edges cut to the curve of the roof
arch. These centers are set up midway between the fan-like strutting
frames previously described. They are usually built of square timbers.
The tie beams are usually 6 × 6 in., and the struts and posts 4 × 4 in.
timbers. The reason for giving the larger sectional dimensions to the
tie beams, contrary to the usual practice in constructing centers, is
that it has to serve as a sill for distributing the pressure to the
foundation of unexcavated soil which supports the center. Sometimes a
sub-sill is used to support the center upon the soil; and in any case
wedges are employed to carry it, which can be removed for the purpose of
striking the center. After the arch is completed, the centers may be
removed immediately, or may be left in position until the masonry has
thoroughly set.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account