The invert masonry is built after the side walls are completed. This is
regarded as a defect of this method of tunneling, since the lateral
pressures may squeeze the side walls together and distort the arch
before the invert is in place to brace them apart. To prevent as much as
possible the distortion of the arch after the centers are removed, it is
considered good practice to shore the masonry with horizontal beams
having their ends abutting against plank, as shown by Fig. 71. These
horizontal beams should be placed at close intervals, and be supported
at intermediate points by vertical posts, as shown by the illustration.
Since the roof arch rests are for some time supported directly by the
unexcavated earth below, settlement is liable, particularly in working
through soft ground. This fact may not be very important so long as the
settlement is uniform, and is not enough to encroach on the space
necessary for the safe passage of travel. To prevent the latter
possibility the centers are placed from 9 ins. to 15 ins. higher than
their true positions, depending upon the nature of the soil, so that
considerable settlement is possible without any danger of the necessary
cross-section being infringed upon. In conclusion it may be noted that
the lining may be constructed in a series of consecutive rings, or as a
single cylindrical mass.
=Hauling.=--Since in this method of tunneling the upper part of the
section is excavated and lined before the excavation of the lower part
is begun, the upper portion is always more advanced than the lower. To
carry away the earth excavated at the front, therefore, an elevation has
to be surmounted; and this is usually done by constructing an inclined
plane rising from the floor of the tunnel to the floor of the heading,
as shown by Fig. 72. This inclined plane has, of course, to be moved
ahead as the work advances, and to permit of this movement with as
little interruption of the other work as possible, two planes are
employed. One is erected at the right-hand side of the section, and
serves to carry the traffic while the left-hand side of the lower
section is being removed some distance ahead and the other plane is
being erected. The inclination given to these planes depends upon the
size of the loads to be hauled, but they should always have as slight a
grade as practicable. Narrow-gauge tracks are laid on these planes and
along the floor of the upper part of the section passing through the
center opening mentioned before as being left in the centers and
strutting.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account