The remaining sections of the tunnel roof were built in the same way,
until the last abutted against the part of the work constructed within
the caisson under the high wooden roof on the Manhattan side of the
river. The following method was adopted for the purpose of connecting
the few parts of the tunnel which had been differently constructed. The
diaphragm at the end of the last section of the tunnel roof was
constructed so as to abut against the last circumferential flanges of
the iron lining without leaving a projecting ring. It was continued
above the metal and concrete lining of the roof in a rectangular form,
and of the same height and width as the wooden bulkhead of the
working-chamber on the Manhattan side of the river. The diaphragm was
made of riveted plates and angles, with an opening 20 ins. by 30 ins.,
bolted so as to be removable at will. The diaphragm was of the same
height as the roof and was connected with a roof-plate to the rangers
supporting the thick wooden roof. Other steel plates, placed vertically,
were riveted to the diaphragm and bolted to the caisson. All this work
was carried on by divers. The wooden bulkhead was cut to the
springing-line of the arch; and between the two parts of the tunnel,
built by different methods, a bulkhead was placed, made of steel plates
14 ins. long, which prevented the entrance of water into the
working-chamber.
[Illustration: FIG. 148.--Showing the Tunnel Completed by Building the
Lower Half within the Caisson.]
When the different sections were joined together, and all the openings
closed and made water-tight, cement-grout was poured on the roof, and
earth was heaped up to a height of 5 ft. The 300 ft. of the roof,
resting on sheeting-piles and provided with diaphragms at the extreme
ends, formed a water-tight working-chamber, or caisson, communicating
with the exterior by means of the shafts and air-locks. The lower
portion of the tunnel was built under air-pressure. The pile-bents were
first cut off at the plane of the tunnel sub-grade, after which the
foundation-bed of concrete was laid. The lower segments of the iron
lining were then placed in position, and the structure made continuous
by building up the lateral walls, consisting of concrete (Fig. 148). No
accidents occurred while building the second part of the tunnel.
The Harlem River tunnel was completed in contract time, although the
opening of the subway was delayed by difficulties encountered in
tunneling through rock in the borough of the Bronx. The writer
endeavored to obtain information regarding the expense per linear foot,
but all his efforts were rewarded with a general assurance that it
proved to be the cheapest method.
SINKING AND JOINING TOGETHER SECTIONS OF TUNNELS BUILT ON LAND. THE
SEINE. THE DETROIT RIVER TUNNELS.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Elsewhere in the archive
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account