| ORDER OF FIRING. | KINDS OF | DEPTH. |CHARGE.| KIND OF |
| | HOLES. | | | DYNAMITE.|
+-------------------+------------+--------+-------+----------+
|Bench { 1st round|4 grading |3′ to 5′|50 lbs.|40% climax|
|Holes { |5 bench |9′ 6″ |45 „ |40% „ |
| { 2nd round|6 trimming |3′ to 9′|42 „ |40% „ |
| | | | | |
|Heading { 3d round |8 center cut|9′ |56 „ |60% „ |
| Holes { 4th round|8 side |8′ |48 „ |40% „ |
| { 5th round|6 dry |8′ |36 „ |40% „ |
+-------------------+------------+--------+-------+----------+
CHAPTER IV.
GENERAL METHODS OF EXCAVATION: SHAFTS: CLASSIFICATION OF TUNNELS.
A number of different modes of procedure are followed in excavating
tunnels, and each of the more important of these will be considered in a
separate chapter. There are, however, certain characteristics common to
all of these methods, and these will be noted briefly here.
[Illustration: FIG. 14.--Diagram Showing Sequence of Excavation for St.
Gothard Tunnel.]
[Illustration: FIG. 15.--Diagram Showing Manner of Determining
Correspondence of Excavation to Sectional Profile.]
=Division of Section.=--It may be asserted at the outset that the whole
area of the tunnel section is not ordinarily excavated at one time, but
that it is removed in sections, and as each section is excavated it is
thoroughly timbered or strutted. The order in which these different
sections are excavated varies with the method of excavation, and it is
clearly shown for each method in succeeding chapters. As a single
example to illustrate the proposition just made, the division of the
section and the sequence of excavation adopted at the St. Gothard tunnel
is selected (Fig. 14). The different parts of the section were excavated
in the order numbered; the names given to each part, and the number of
holes employed in breaking it down, are given by the table on page 35.
Whatever method is employed, the work always begins by driving a
heading, which is the most difficult and expensive part of the
excavation. All the other operations required in breaking down the
remainder of the tunnel section are usually designated by the general
term of enlargement of the profile. The various operations of excavation
may, therefore, be classified either as excavation of the heading or
enlargement of the profile.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account