Tunnels are classified in various ways, but the most logical method
would appear to be a grouping according to the quality of the material
through which they are driven; and this method will be adopted here. By
this method we have first the following general classification: (1)
Tunnels in hard rock; (2) tunnels in ordinary loose soil; (3) tunnels in
quicksand; (4) open-cut tunnels; and (5) submarine tunnels. It is hardly
necessary to say that this classification, like all others, is simply
an arbitrary arrangement adopted for the sake of order and convenience
in treating the subject.
=Tunnels in Hard Rock.=--With the numerous labor-saving methods and
machines now available, hard rock is perhaps the safest and easiest of
all materials through which to drive a tunnel. Tunnels through hard rock
may be excavated, either by a drift or by a heading. The difference
depends upon whether the advance gallery is located close to the floor
or near the soffit of the section.
=Tunnels in Loose Soils.=--In driving tunnels through loose soils many
different methods have been devised, which may be grouped as follows:
(1) Tunnels excavated at the soffit--Belgian method; (2) tunnels
excavated along the perimeter--German method; (3) tunnels excavated in
the whole section--English, Austrian and American methods; (4) tunnels
excavated in two halves independent of each other--Italian method.
(1) Excavating the tunnel by beginning at the soffit of the section, or
by the Belgian method, is the method of tunneling in loose soils most
commonly employed in Europe at the present time. It consists in
excavating the soffit of the section first; then building the arch,
which is supported upon the unexcavated ground; and finally in
excavating the lower portion of the section, and building the side walls
and invert.
(2) In excavating tunnels along the perimeter an annular excavation is
made, following closely the outline of the sectional profile in which
the lining masonry is built, after which the center core is excavated.
In the German method two drifts are opened at each side of the tunnel
near the bottom. Other drifts are excavated, one above the other, on
each side to extend or heighten the first two until all the perimeter is
open except across the bottom. The masonry lining is then built from the
bottom upwards on each side to the crown of the arch, and then the
center core is removed and the invert is built.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account