(3) This method, as its name implies, consists in taking out short
lengths of the whole sectional profile before beginning the building of
the masonry. In the English method the invert is built first, then the
side walls, and finally the arch. The excavators and masons work
alternately. The Austrian method differs in two particulars from the
English: the length of section opened is made great enough to allow the
excavators to continue work ahead of the masons, and the side walls and
roof are built before the invert. In the American method the whole
section of the tunnel is open at once: excavators and masons work
simultaneously, but a very large quantity of timbering is required.
(4) The Italian method is very seldom employed on account of its
expensiveness, but it can often be used where the other methods fail. It
consists in excavating the lower half of the section, and building the
invert and side walls, and then filling the space between the walls in
again except for a narrow passageway for the cars; next the upper part
of the section is excavated, as in the Belgian method, and the arch is
built; and finally the soil in the lower part is permanently removed.
=Tunnels in Quicksand.=--Tunnels through quicksand are driven by one of
the ordinary soft-ground methods after draining away the water, or else
as submarine tunnels.
=Open-Cut Tunnels.=--Open-cut tunnels are those driven at such a small
depth under the surface that it is more convenient to excavate an open
cut, build the tunnel masonry inside it, and then refill the open
spaces, than it is to carry on the work entirely underground. In firm
soils the usual mode of operation is to excavate first two parallel
trenches for the side walls, then remove the core, and build the arch
and the invert. In unstable soils, since the invert must be built first,
it is usual to open up a single wide trench. In infrequent cases where a
tunnel is desired in a place which is to be filled in, the masonry is
built as a surface structure, which in due time is covered.
=Submarine Tunnels.=--The mode of procedure followed in excavating
submarine tunnels depends upon whether the material penetrated is
pervious or impervious to water. In impervious material any of the
ordinary methods of tunneling found suitable may be employed. In
pervious material the excavation may be accomplished either by means of
compressed air to keep the water out of the excavation, or by means of a
shield closing the front of the excavation, or by a combination of these
two methods. Tunnels on the river bed are built by means of coffer dams
which inclose alternate portions of the work, by sinking a continuous
series of pneumatic caissons and opening communication between them, and
by sinking the tunnel in sections constructed on land.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account