Fig. 115 is a sketch of a hollow cylindrical water-jet pile, which has
been used successfully in cases of light sand. The lower end of the
pile is made externally in the form of a solid disc, terminating in a
conical point, having an aperture in the centre to correspond to the
water-jet. To the top of the pile is secured a tight-fitting cover
through which a tube passes from a force pump. Water at high pressure
is pumped into the tube, and as it forces its way out through the
conical point the sand is stirred up and loosened, and thus allows the
pile to descend. When the pile has been lowered to a sufficient depth
the pumps and tube are removed, and the sand settles down into its
former compact condition.
Great care must be used with the first two or three lengths of any
screw pile to ensure the pile taking a correct or true vertical
position. Each series of screw piles should be properly braced
together to obtain stability under moving loads.
[Illustration: Fig. 116]
[Illustration: Fig. 117]
Hollow cylinders of cast-iron, wrought-iron, or steel form most
efficient foundations or piers for large bridges over soft ground or
fresh water of considerable depth. Made open at the bottom, and
constructed of complete rings, or, if of large diameter, of rings
built up in segments and securely attached together with water-tight 119
joints, the cylinder is placed in its proper position on the ground or
lowered into the water preparatory to sinking. The lower length is
made with a sharp cutting edge to facilitate penetration. By
excavating and removing the material round the cutting edge and base
inside the lower length, the cylinder descends gradually either from
its own weight or by assisted weights, and length after length is
added until it is sunk to the depth required. The excavated material
is filled into buckets and hoisted to the surface by a winch fixed on
the top length. When sinking in water the working top of the cylinder
is always kept at a suitable height above the water for convenience in
removal of the earth or clay from the interior to barges or gangways
alongside.