A section of the San Leandro Dam, near Oakland, Cal., is shown by
Fig. 31. This section was supplied by Mr. W. F. Boardman, hydraulic
engineer, who superintended the construction of the dam, from his own
private notes and data. It differs materially from sections heretofore
published, and is 5 ft. higher, thus making it rank as the highest
earth dam in the world of which we have an authentic record.
The dam was commenced in 1874, and brought up to a height of 115 ft.
above the bed of the creek in 1898. At the present time it is 500 ft.
in length on the crest and 28 ft. wide. The original width of the
ravine at the base of the dam was 66 ft. The present width of base
from toe to toe of slopes is 1,700 ft. The height of embankment above
the original surface is 125 ft., with a puddle trench extending 30 ft.
below.
[Illustration: FIG. 30.–CROSS-SECTION OF UPPER PECOS RIVER DAM;
COMBINED ROCK FILL AND EARTH.]
[Illustration: FIG. 31.–DEVELOPED SECTION OF SAN LEANDRO DAM.]
All that portion of the dam within a slope of 2½ on 1 at the rear and
3 on 1 at the face is built of choice material, carefully selected and
put in with great care. The portion outside of the 2½ on 1 slope line
at the down-stream side of the dam, was _sluice in_ from the adjacent
hills regardless of its character, and is composed of ordinary soil
containing more or less rock.
This process of sluicing was carried on during the rainy season, when
there was an abundance of water, and it was intended to be continued
until the canyon below the dam had been filled to an average slope of
6.7 on 1 at the rear of the dam. It was thought that the location was
particularly favorable for this kind of construction, the original
intention being to raise the dam from time to time, not only to
increase the storage as the demand for water increased, but to meet
the annual loss in capacity caused by the silting up of the reservoir
basin. The latter has amounted to about 1 ft. in depth per annum.
METHOD OF CONSTRUCTION.–Under the main body of the dam, the surface was
stripped of all sediment, sand, gravel and vegetable matter. Choice
material, carefully selected, was then brought by carts and wagons and
evenly distributed over the surface in layers about 1 ft. or less in
thickness. This was sprinkled with just enough water to make it pack
well, not enough to make it like mud. During construction a band of
horses was led by a boy on horseback over the entire work, to compact
the materials and assist in making the dam one homogeneous mass. No
rollers were used on this dam.
The central trench was cut 30 ft. below the original bed of the creek.
In the bottom of this trench three secondary trenches, 3 ft. wide by 3
ft. deep, were made and filled with concrete. These concrete walls were
carried up 2 ft. above the general floor of the trench, to break the
continuity of its surface.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account