[Illustration: _Two assembly operations and system checkouts are
performed separated by a trip to the pad to verify compatibility
with the launch vehicle_]
[Illustration: _A complete electronic checkout station in the hangar
supports the spacecraft to ensure operability_]
[Illustration: _Mariner takes form as the solar panels are attached
and the final hangar checkout operations are performed before the
launch._]
[Illustration: _Wrapped in a dust cover, the spacecraft is
transferred from Hangar AE at AMR to the explosive safe area for
further tests._]
[Illustration: _Inside the bunker-like explosive safe area, the
powerful midcourse maneuver rocket engine is installed in the center
of the spacecraft._]
[Illustration: _Final assembly and inspection complete, Mariner is
“canned” in the nose shroud that will protect it through the Earth’s
atmosphere and into space._]
[Illustration: _At the pad, the shrouded spacecraft is lifted past
the Atlas ..._]
[Illustration: _... and the Agena._]
[Illustration: _Twelfth floor: Mariner reaches its mating level._]
[Illustration: _The spacecraft is eased over to the top of the Agena
..._]
[Illustration: _... and carefully mated to it._]
The second launch attempt started at 6:37 p.m., August 26, with the
Atlas-Agena B and Mariner II ready on the pad. At 9:52 p.m., T minus 100
minutes, a 40-minute hold was called to replace the Atlas main battery.
By 10:37, with 95 minutes to launch, all spacecraft systems were ready
to go.
A routine hold at T minus 60 minutes was extended beyond 30 minutes in
order to verify the spacecraft battery life expectation. At 11:48 p.m.,
with the count standing at T minus 55 minutes, the spacecraft, the
vehicles, the Range, and the DSIF were all given the green light.
When good launching weather was reported at 12:18 a.m., August 27, just
25 minutes from liftoff, a cautious optimism began to mount in the
blockhouse and among the tired crews.
But the tension began to build again. The second prescheduled hold at T
minus 5 minutes was extended beyond a half-hour when the radio guidance
system had difficulty with ground station power. Counting was “picked
up” and the clock continued to move down to 60 seconds before liftoff.
Suddenly, the radio guidance system was in trouble again. Fluctuations
showed in its rate beacon signals, and another hold was called. Still
another hold for the same reason followed at T minus 50 seconds. This
time, at 1:30 a.m., the count was set back to T minus 5 minutes.
One further crisis developed during this hold—only 3 minutes of
pre-launch life remained in Atlas’ main battery. A quick decision was
made to hold the switchover to missile power until T minus 60 seconds to
help conserve the life of the battery.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account