The Industrial Canal and Inner Harbor of New Orleans: History, Description and Economic Aspects of Giant Facility Created to Encourage Industrial Expansion and Develop Commerce — John Shaqi
The Industrial Canal and Inner Harbor of New Orleans: History, Description and Economic Aspects of Giant Facility Created to Encourage Industrial Expansion and Develop CommerceDabney, Thomas Ewing
History
The Industrial Canal and Inner Harbor of New Orleans: History, Description and Economic Aspects of Giant Facility Created to Encourage Industrial Expansion and Develop Commerce
Dabney, Thomas Ewing
Canals -- Louisiana; New Orleans (La.) -- Harbor
George M. Wells, consulting engineer, in his report of December 9,
1918, to the Dock Board, summarized labor increases over the scale when
the work was begun, as follows: Unskilled labor, 54%; pile driver men,
40%; machinists, 40%; blacksmiths, 40%; foremen and monthly, 15 to
40%--an average increase of 40%. Materials had advanced, he went on to
show, as follows: Gravel, 72%; sand, 25%; cement, 10%; lumber (form),
70%; timber, 40%; piles, untreated, 40%; piles, treated, 25%. These
increases, together with the expansion of the plans requiring a canal
of maximum depth, instead of the pilot cut of fifteen feet, as
originally planned; the insistence of the Levee Board that levees in
the back areas must be raised to elevation 30; development of
unforeseen and unforeseeable quicksand conditions in the various
excavations; requirements of railroads for bridges of greater capacity
and strength than needed; building of a power line to the Foundation
Company's plant--not a Dock Board job, but one that the conditions
required it should finance then; and other expenses, besides delaying
the work, made another bond issue necessary to finish the job.
At its meeting of February 26, 1919, President Thompson laid the matter
before the board. It decided to issue $6,000,000 of bonds, for which
the same syndicate of bankers that had taken the other two offered 96.
Liberty bonds were then selling at a big discount, and this seemed the
best terms on which the money could be secured.
This gave a total issue of $12,000,000 to date, the interest on which
amounted to $600,000 a year. The Levee Board raised its share of the
"rental" to $550,000, to guarantee the interest; the Public Belt
Railroad's $50,000 made the total complete.
In the meantime ships were beginning to bulk large on the ways of the
Foundation and the Doullut & Williams yards. The Foundation company
launched its first, the Gauchy--a 4,200-ton non-sinkable steel ship,
built for the French government--in September, 1919; and the Doullut &
Williams company launched its first, the New Orleans, a steel vessel of
9,600 tons, the largest turned out south of Newport News, built for the
Shipping Board, in January, 1920. These were followed by four sister
vessels from the Foundation yard and seven from the Doullut & Williams
plant. The former went to sea through Bayou Bienvenu and the latter
through Lake Pontchartrain. The Doullut & Williams yard is a large one.
Originally planning a mere assembling yard, the Foundation Company had
subsequently developed the greatest steel fabricating plant in the
South--so confident it was that New Orleans would carry through the
project.
And, too, the New Orleans Army Supply Base that Uncle Sam was building
on the river end of the Industrial Canal was rapidly rising--the
facility that was to double the port storage capacity of New Orleans
when it was finally completed in June, 1919.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account