Earth excavation:
Stripping dam base, 85,200 cubic yards, at $0.30 $25,560
Core wall trench, 26,000 cubic yards, at $1 26,000
Rock excavation, 10,600 cubic yards, at $2 21,200
Rock fill in dam, 214,000 cubic yards, at $1.25 267,500
Rubble masonry, 24,500 cubic yards, at $5 122,500
Concrete, 30,500 cubic yards, at $6 183,000
Gate chambers and tunnels 65,000
Reconstruction of highways 142,400
Reconstruction of railroads 815,000
Real estate 1,435,000
----------
3,103,160
Engineering and contingencies 336,840
----------
3,440,000
Protection of Newark pipe line 20,000
----------
Total cost 3,460,000
The final recommendation of the committee involves the
consideration of two projects for flood storage, one on Great Piece
Meadow and the other above Mountain View on the Pompton. In making
such recommendations the committee is of the opinion that it must
take into account matters of engineering policy with regard to
future needs and contingencies, as well as the bare necessities of
the present.
If there were none other than the single problem of prevention the
committee would advise the construction of the reservoir on Great
Piece Meadow by reason of its smaller probable cost and its equal
efficiency. It is plain, however, that there are many important
features of public policy involved in the subject at hand.
Population in the valley of the Passaic is developing so rapidly
that in only a few years the present sources of water supply will
be inadequate. The whole subject of water supply for northern New
Jersey demands immediate consideration, and it would not be wise to
take up the matter of prevention of flood damage in the Passaic
without basing the value of every project upon its adaptability
for use in future water-supply needs.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account