engine, was installed at the top of
the shaft, and this kept the tunnels reasonably clear of smoke at all
times. After the bench and enlargement had passed the bottom of the
shaft, the use of the fan was abandoned, as it was found that the
tunnels cleared themselves fairly well, probably owing to the larger
cross-section reaching all the way to the Shaft. What little fog and
smoke there might be did not cause enough trouble to warrant the cost of
running the fan, which, owing to its location, required the whole time
of a mechanic in attendance day and night.
_Lighting._--During the earlier stages of the work, gasoline lamps and
Kitson lights were used. The former, of the familiar banjo type, and a
modification of this, with a section of wrought-iron pipe for the
reservoir, were very unsatisfactory, and were out of repair and leaking
a large proportion of the time. The Kitson lights were given only a
short trial, but were found unsatisfactory, owing to the necessity of
moving them frequently and having to set them up in insecure positions.
Electric lights were installed by Mr. Bradley, on his assumption of the
contract.
The number of lamps maintained in each of the tunnels for the excavation
was approximately as follows:
At the main working face From 8 to 10
On and around the shovel ” 9 to 12
Between the portal and the working face ” 60 to 80
The cost of lighting for the whole work averaged about 15 cents per
cu. yd., which is quite large. This was mainly due to the fact that
current was bought from outside sources during a large part of the time
(one-third of the yardage). Part of this current cost 5 cents per
kw-hr., and there were fairly heavy charges for connecting the tunnel
wiring system with the source of supply. Current bought from the Public
Service Corporation cost from 10 to 12 cents per kw-hr. delivered at the
mouth of the tunnel.
_Pumping._--The quantity of water encountered during the excavation of
the tunnels, measured somewhat roughly, was approximately as follows:
At Weehawken 74 gal. per min.
At Central Shaft 1 ” ” ”
At Hackensack 18 ” ” ”
The water at the Weehawken end had to be pumped from the bottom of the
shaft, a lift of about 90 ft., while at the Hackensack end it had to be
pumped back from the face up grade to the portal.
The cost of pumping was about $100 to $125 per month for labor for the
whole work, besides the cost of the plant (about $1,200) and the power
for running it.
PROGRESS.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account