Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910: The Bergen Hill Tunnels. Paper No. 1154Lavis, F.
History
Transactions of the American Society of Civil Engineers, vol. LXVIII, Sept. 1910: The Bergen Hill Tunnels. Paper No. 1154
Lavis, F.
Civil engineering -- Periodicals; Railroad tunnels -- Design and construction
Aside from the fact that neither type was a success, neither of these
schemes was much improvement over the belt, inasmuch as only one batch
could be handled at a time, owing to the necessity of using the engine
to haul the cars back and forth on the platform. The final solution was
found in the use of the traveling gantry, shown by Fig. 12 and Fig. 1,
Plate XXVI, the latter being one of the arch gantries. The gantry used
for the bench- and sand-walls was supported on framed bents on wheels
running on rails laid on the foundation; that for the arch was the same,
except that the high-framed bent was dispensed with, the side-sills
resting directly on the journals of wheels traveling on rails on top of
the finished bench-wall.
These gantries were used only as a means of hoisting the buckets and
moving them along to where they could be dumped directly on the
platform, whence the concrete was shoveled into wheel-barrows, which
could be dumped directly into the bench-walls; or, in the case of the
arches, shoveled from the platform of the gantry to the intermediate
platform on the arch ribs, and thence directly into the arch. This use
of wheel-barrows, though apparently a somewhat crude method and a
retrogression from the use of the belt conveyor, proved very successful,
and really involved no more labor than did the conveyors, although this
might not have been the case had these latter worked as they were
originally designed to.
The method finally adopted allowed as many as four buckets to be dumped
on the platform on one end of the arch gantry at one time, and eight on
one end of that used for the bench-walls, the workmen handling about
three of these latter into the forms by the time the last of the eight
was dumped. It required about 1½ min. to place a car under the gantry,
hoist the bucket, dump, close it, and return it to the car below.
Rock packing was stored at the other end of the platform, for use as
required, when it was not handled directly from the end nearest the
work. This method allowed the concrete and other materials to be brought
in in trains at infrequent intervals, and provided a sufficient supply
of material on hand so that the men handling it on top could be kept
steadily at work.
Each hoisting engine on these gantries had 7 by 10-in. cylinders, and a
double drum; some of them were Lamberts and some Mundys, operated by
compressed air.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account