When a railway line is to be carried across a range of mountains or
hills, the first question which arises is whether it is better to
construct a tunnel or to make such a détour as will enable the
obstruction to be passed with ordinary surface construction. The answer
to this question depends upon the comparative cost of construction and
maintenance, and upon the relative commercial and structural advantages
and disadvantages of the two methods. In favor of the open road there
are its smaller cost and the decreased time required in its
construction. These mean that less capital will be required, and that
the road will sooner be able to earn something for its builders. Against
the open road there are: its greater length and consequently its heavier
running expenses; the greater amount of rolling-stock required to
operate it; the heavy expense of maintaining a mountain road; and the
necessity of employing larger locomotives, with the increased expenses
which they entail. In favor of the tunnel there are: the shortening of
the road, with the consequent decrease in the operating expenses and
amount of rolling-stock required; the smaller cost of maintenance,
owing to the protection of the track from snow and rain and other
natural influences causing deterioration; and the decreased cost of
hauling due to the lighter grades. Against the tunnel, there are its
enormous cost as compared with an open road and the great length of time
required to construct it.
To determine in any particular case whether a tunnel or an open road is
best, requires a careful integration of all the factors mentioned. It
may be asserted in a general way, however, that the enormous advance
made in the art of tunnel building has done much to lessen the strength
of the principal objections to tunnels, namely, their great cost and the
length of time required for their construction. Where the choice lies
between a tunnel or a long détour with heavy grades it is sooner or
later almost always decided in favor of a tunnel. When, however, the
conditions are such that the choice lies between a tunnel or a heavy
open cut with the same grades the problem of deciding between the two
solutions is a more difficult one.
It is generally assumed that when the cut required will have a vertical
depth exceeding 60 ft. it is less expensive to build a tunnel unless the
excavated material is needed for a nearby embankment or fill. This rule
is not absolute, but varies according to local conditions. For instance,
in materials of rigid and unyielding character, such as rock, the
practical limit to the depth of a cut goes far beyond that point at
which a tunnel would be more economical according to the above rule. In
soils of a yielding character, on the other hand, the very flat slope
required for stability adds greatly to the cost of making a cut.
Public-domain text, read in full here on John Shaqi.
Reviews
Reviews
No reviews yet
Be the first to share your thoughts on this work.
Join the Discussion
Join the discussion
Sign in to leave a comment or review.
Sign InorCreate an account