When the centre line of the tunnel has been accurately set out on the
ground, and the levels of the different parts of the work decided, the
construction of the shafts and the driving of the headings can be
commenced. Working shafts intended to serve for permanent ventilation
are generally made nine or ten feet or more in diameter, and are
usually lined with substantial brickwork or masonry. When the well-like 168
excavation has been carried down a few yards, or as far as it can be
taken without the risk of the earth falling in upon the sinkers, a
strong curb of hard wood or iron of the same diameter as the finished
shaft is laid down perfectly level and to exact position, and on this
curb the ring or lining of brickwork or masonry is built up to the
level of the ground. The first length finished, the excavation
downwards is resumed, and the interior lining continued, either by
allowing the first length to slide down as the material below is
gradually removed, and building further lining on the top, or by
excavating and propping up the curbing with strong timbers below. When
working to the latter method, stout wooden props of convenient length,
stepped on to sole-pieces, are adjusted to the under side of the
wooden curb above, the material is then removed for the thickness of
the brickwork or masonry, and another curb accurately set to level and
position; on this is built a length of lining up to the first curb.
This work of under-building or under-pinning must be carried out with
great care and in segments; no props must be removed until the curb
immediately above is well supported by the new lining, and the inside
of the lining must be watched and tested to prevent any tilting. All
spaces at the back of the work must be filled in and well packed with
hard dry material. As the shaft is continued downwards the mode of
working may have to be varied; different descriptions of material may
be encountered, and blasting, shoring, and pumping may each in turn be
necessary.
When down to the full depth, the lower length of the shaft will have
to be securely supported by strong timbers, until it can be properly
built into and incorporated with the arching of the tunnel or side
gallery.
The completion of the shaft enables the workings to be commenced on
each side, the excavated material can be hoisted to the surface, and
building material lowered down. When the tunnel works are finally
finished, the lining of the shaft should be carried up until it is 15
or 20 feet above the level of the surface of the ground, and a
dome-shaped iron grating placed on the top as a protection against
stones or other articles which malicious persons might attempt to
throw down the shaft.