Figs. 202 and 203 give end view and longitudinal section of timber
framework frequently adopted for average tunnel work. The positions of
the different pieces will explain themselves and the duty they have to
perform. The main struts, or raking pieces, which have to sustain
great pressure, may be shored against the finished lengths of masonry
or brickwork. The timbering of the sides can be removed as the lining
proceeds, but in many cases the round logs and boards near the crown
cannot be withdrawn, and have to be left in the work, the space
between the top of the arching and under side of the boards being
firmly packed with brickwork, masonry, or dry rubble stonework.
As the tunnel lining is generally carried forward in short lengths,
following up the main excavations, the centering for the arching
should be of such description that it can be readily transferred or
moved forward as the work proceeds. The form of the centering, and the
spacing of its upright supports, must admit of sufficient width for
one or more lines of rails for the waggons required to remove the
excavated _débris_ and convey the building materials used in the
lining.
Picks, bars, and shovels are the tools used in the excavation of the
softer material and loose disintegrated rock, but for the hard rock,
blasting will be necessary. The tunnel opening being comparatively
small, only moderate blasting charges can be used with safety, and
these must be placed so as to break up the rock-bed in a suitable
manner for working, and without shaking or damaging the already
completed excavation. Ordinary hand-drills, or _jumpers_, may be used
for forming the charge holes, a number of them being at work at the
same time, and the charges fired very closely one after the other. As
the blasting operations necessitate the retiring of the miners to a
considerable distance, out of the way of flying fragments, and the
remaining away until the foul air has been dispelled, it is advisable
to fire off several charges about the same time, and thus minimize as
much as possible the stoppage to the drilling and clearing away the
loosened material.
[Illustration: Fig. 204, 205, 206, 207, 208, 209, 210, 211]
Mechanical drills, worked by compressed air or other motive-power, are
now very extensively used where the rock is solid and continuous. They
are much more expeditious than the hand drills, but they are costly in 174
their installation, and also in their working and maintenance.
In some tunnels, where the material has been firm and dry, the upper
portion of the excavation has been first removed, and the masonry and
brickwork lining built in position down to about the springing of the
arch, the remainder of the excavation being afterwards taken out, and
the side walls built by means of shoring and underpinning.