Cases will arise where it will be necessary to make a shallow cutting
through boggy peaty ground. If the boggy material be very soft, and
its thickness from the formation level to the solid ground below be
not great, it may be advisable to remove this extra thickness down to
the hard lower bed, and fill in up to formation level with strong
material. If, however, the bog or peat be too thick to justify its
entire removal, it should be excavated say down to two feet below
formation level, and a thick layer of branches of trees and strong
brushwood closely laid and packed the full width of the road-bed. On
this preparatory foundation must be placed good clean ballast to carry
the permanent way. Two or three extra sleepers should be allowed to
the rail length, and in some instances it will be necessary to
introduce two, or even four, rows of strong longitudinal timbers--half
balks--under the transverse sleepers. The object of all this extra
timber is to obtain a large increase of bearing area on the soft
yielding surface of the boggy material. Notwithstanding these special
precautions, the trackway will sink down a little during the passage
of an engine or train, but will generally return to its former level.
Good side drains or water-tables should be formed at each side of the
cutting to take away all rain and surface water.
In all cuttings it is desirable to have the line of formation on a
slight gradient, sufficient to carry away all rain water or spring
water which may be collected in the water-tables; but more 66
particularly so is this necessary in a rock cutting, where the
material, being non-absorbent as compared with earth or gravel,
requires that all drainage must be carried away to the mouth of the
cutting.
In carrying out railway embankments and road approaches, it is usual
to form the sides to a slope of 1½ to 1, as shown on Fig. 56.
Occasionally the cuttings produce material which might stand at a
rather steeper slope, but considering the effects which might
afterwards be produced by heavy rains falling on the sides, it is more
prudent to adopt the flatter slope of 1½ to 1. Some descriptions of
clay will not stand at the above slope, but require a slope of 2 to 1,
or even 3 to 1.
When proceeding with the earthworks, it is customary to first remove
and lay aside a layer, say 9 inches in depth, of soil and earth from
the seat of the embankments and top widths of the cuttings, to be used
afterwards in soiling the trimmed and finished slopes of the cuttings
and embankments. This soil being removed, the actual work of the
excavation can be commenced. The working longitudinal section will
give all the necessary particulars as to position of the mouths of the
cuttings and the depths at the various chain-pegs, and the top widths
of the cuttings can be ascertained by calculation, if on even ground,
or from the cross-sections if on side-lying ground, according as the
material may be earth, clay, or rock.