The _swing_-bridge arrangement is so simple in construction,
convenient for inspection, and easy to maintain, that where possible
it is now generally adopted in preference to any other system. The 89
weights on centre pin and roller path may be distributed as considered
most expedient, and by means of suitable appliances the weight may be
altogether taken off the centre and rollers when the bridge is closed
for the passage of trains.
There are many wide rivers which, although not navigable in the
ordinary acceptance of the term, nevertheless require bridges of large
spans to provide free waterway for the floating down of rafts of
timber. Away in the high ground, in the timber-growing districts,
trees are felled, sawn or cut into long poles, logs, or scantlings,
and hauled to the banks of the river. The timbers are then formed into
large rafts of the most convenient form for floating down to the place
of distribution or port for shipment. Even with old experienced
floaters, using their long sweeps in the most skilful manner, it is
difficult to take anything but a very irregular course down the
stream. Under the most favourable circumstances one of these large
rafts is an unwieldy, awkward craft to manage; but in a river full of
twists and turns, with reaches varying from comparative smooth water
to miniature rapids, the current carries the huge mass surging along,
and only a clear, unobstructed channel will enable its navigation to
be carried out with safety. The presence of a pier in the main
waterway might cause destruction to the rafts and loss of life to the
men. The vested interests in floating rights are tenaciously guarded,
and no new bridge would be sanctioned which would in any way interfere
with the waterway or endanger the passage of rafts down the river.
Bridges of this description are much less costly than those over deep
water--navigable rivers. Excepting the large spans, the rest of the
work is comparatively simple. The water is generally shallow, and much
reduced in quantity during the summer months. Good foundations can
generally be obtained without going to any great depth. The headway
may be kept low, or of such height as may best suit the purposes of
the railway, and be sufficiently well up out of the way of the floods
which may take place from time to time on the river.
[Illustration: Fig. 89, 90]
Fig. 86 is a sketch of a bridge constructed over a river much used for
rafting purposes. The large span is over the main channel, and the
small spans are over a wide gravelly foreshore, which is only covered
with water during exceptionally high floods in the autumn or winter. 91
No rafting can be carried on when the river is in flood; the current
would be too strong to permit of the raft being kept under control.
Fig. 87 is a sketch of a similar bridge where the river is confined to
a regular channel between two sloping banks of strong clay.