Fig. 88 shows a bridge erected over a narrow rocky pass in the river.
The channel is hemmed in by the almost perpendicular sides of mountain
granite, there are no banks to overflow, the flood waters cannot
spread laterally, however much they may increase in depth, and with
building-stone at hand in abundance, and foundations formed in the
solid rock, the situation is one of the most favourable for a strong
permanent bridge. The cast-iron arch of 150-feet span has a graceful
appearance, and harmonizes well with the surrounding scenery. A small
masonry arch at each end of the bridge provides for communication
along the banks of the river.
With rivers which are neither under the control of navigation
authorities nor used for rafts of timber, there is much greater
freedom for the designing and carrying out of bridges or viaducts
suitable for the actual physical conditions of the locality. The
headway will be guided only by the height of the railway to be carried
across, and by any flood-water levels which may affect the work. The
size of the spans will be regulated by the width of the river, the
depth of the water, and the nature of the ground into which the piers
have to be built. For broad, shallow rivers with good firm river-beds,
piers may be built at moderate cost, and comparatively small spans
adopted; on the other hand, with a broad deep river it will be better,
as previously explained, to reduce the number of piers and increase
the span. In the one case, for example, a river 150 feet wide may be
crossed with three spans and two piers in the shallow water, as in
Fig. 89; in the other it may be more prudent and economical to cross
in one span, without any intermediate pier, as shown in Fig. 90.
[Illustration: Fig. 91]
Next in importance to the large bridges and viaducts over rivers are
the viaducts which have to be constructed for the crossing of deep
inland valleys. The occurrence of one of these deep valleys between
long lengths of average table-land renders necessary either a series
of cuttings and falling gradients to get down to a low level, or the
erection of high-level works to continue onward the rail-level at the 93
height already attained. A decision to adopt the latter course brings
forward the consideration as to the method of carrying out the work.
To form a high embankment across such a valley would entail an
enormous expenditure for earthwork, and several openings, or bridges,
would have to be made in the embankment for streams, rivers, and
roadways. Instead, therefore, of making this part of the line entirely
of embankment, it is usual to carry the earthwork forward until the
height is about 25 or 30 feet, and to form the remainder of the
opening of arching, as shown in Fig. 91.
This arrangement is not only less costly than an embankment of such
height, but has also the great advantage that any or all of the arches
are available for the passage of streams, rivers, roads, and
accommodation works.