Arch bridges may be built of masonwork or brickwork, or a combination
of the two. If the available quarries do not yield good flat bedded
stones readily worked, it is better, where possible, to use strong
hard bricks for the arching, and utilize the stone for the remainder
of the work.
Although arching undoubtedly forms the most durable type of
bridgework, numbers of cases occur where the available height or space
between rail-level and road-level is too small, or the cost of masonry
and brickwork too great, to admit of anything but girder-work.
Detailed sketches of some of the many forms of girder bridges are
given in Figs. 132 to 153, illustrating various systems of roadways
and parapets. In some instances the main girders are made sufficiently
deep to serve as parapets, while in others a shallower girder has been
adopted, on top of which has been placed a light cast-iron parapet
composed either of close plate-work or of ornamental open railings.
The open ironwork parapet has a good appearance, but as a screen is
not so efficient as the close cast-iron plates.
In addition to the bridges required for the regular public roads, it
is usually necessary to construct a certain number of occupation or
private road bridges over and under the line to accommodate portions
of estates and large properties intersected or severed by the railway,
and which would be inadequately provided for by ordinary gate
crossings on the level. The position and description of these
occupation bridges is generally matter of private arrangement. The
bridges will be somewhat similar in character to the public road 111
bridges, but of much less width for the roadway. Those over the
railway must have the standard span and height adopted as a minimum
for the other over-line bridges, and those under the railway must have
the full width on the top for the lines of rails, but will have less
width between the abutments for the roadway.
Foundations.--So much depends upon the soundness and security of the
foundations of any bridge, viaduct, or large building, that it would
be almost impossible to devote too much care to the selection and
treatment. Unless the foundation be firm, the entire structure will be
exposed to the risk of failure, either in subsidence of masonry,
giving way of arches, or depression of girders. A small matter
overlooked during the construction of this part of the work will be
most difficult to correct or adjust afterwards.
The insistent weight of all structures built of masonry or brickwork
will cause the mass to settle to a certain extent, according as the
joints of mortar or cement become compressed by the number of
superincumbent courses. In a similar manner the gravel and clay of a
foundation will compress more or less according to its compactness and
the weight of the structure. No inconvenience will, however, arise if
the settlement or compression be uniform throughout the entire area.